Master Plan Update - Florida's Turnpike

Master Plan Update - Florida's Turnpike

Master Plan Update - Florida's Turnpike

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

available revenues, the estimated time frame when<br />

the project is needed, and the relative need of a<br />

given project in relation to all other project needs,<br />

projects may first be listed as <strong>Turnpike</strong> unfunded<br />

needs projects.<br />

Project <strong>Plan</strong>nIng Process<br />

25-Year<br />

Needs<br />

<strong>Plan</strong><br />

<strong>Turnpike</strong><br />

<strong>Master</strong><br />

<strong>Plan</strong><br />

10-Year<br />

Finance<br />

<strong>Plan</strong><br />

5-Year Work Program<br />

ADOPTED<br />

Five-Year<br />

Work Program<br />

FY 1<br />

FY 2<br />

FY 3<br />

FY 4<br />

FY 5<br />

annUal Work Program UPdate Process<br />

Annual<br />

Work Program<br />

<strong>Update</strong><br />

Remove FY 1<br />

FY 2<br />

FY 3<br />

FY 4<br />

FY 5<br />

FY 6<br />

Add FY 6<br />

FY 2011 - FY 2035<br />

3.2 fIve-Year Work Program<br />

1. 2. 3.<br />

the turnpike earns revenues from toll collections<br />

and concession fees on its 460 miles of limitedaccess<br />

tolled facilities. a capital improvements<br />

program called the five-Year Work Program is<br />

developed from a combination of turnpike toll and<br />

concession revenues and from bond proceeds<br />

obtained by leveraging those revenues. though<br />

the turnpike is generally a self-funded entity,<br />

the five-Year Work Program may also contain<br />

federal funding awards and/or private developer<br />

funding contributions toward projects. generally,<br />

private entities who propose projects to serve<br />

their developments are expected to pay for those<br />

projects.<br />

The Five-Year Work Program is a financially feasible<br />

document containing all of the turnpike capital<br />

improvement projects that are funded for a<br />

five-year time period by phase, funding type,<br />

and year. the five-Year Work Program is updated<br />

annually to reflect the next five-year time frame of<br />

project funding by dropping the current or first year<br />

of funding and adding a new outer or fifth year<br />

of funding. In the fall of each year, the turnpike<br />

develops a tentative five-Year Work Program that<br />

is presented to the local governments at public<br />

hearings conducted by metropolitan <strong>Plan</strong>ning<br />

organizations (mPos) or, in rural areas, by county<br />

TENTATIVE<br />

Five-Year<br />

Work Program<br />

FY 1<br />

FY 2<br />

FY 3<br />

FY 4<br />

FY 5<br />

3