For recipients with projects affected by Circular 5200.1A, Chapter II, Section 6, Safety and Security<br />
Management Plan, the SSMP Review will be part of the evaluation of an updated PMP submitted to <strong>FTA</strong><br />
with application for FFGA or during a later project phase. These reviews will be conducted for projects<br />
that have been grandfathered from the requirements of Circular 5800.1 and must continue to follow the<br />
SSMP requirements specified in Chapter II, Section 6 of <strong>FTA</strong>’s FFGA Circular 5200.1A although<br />
applicable criteria identified in Section 6.1.3.2 should be considered as the SSMP is updated at various<br />
stages of the project.<br />
6.2.1 SSMP Review<br />
Following Chapter II, Section 6 of Circular 5200.1A and the DRAFT Guidance for the Development of<br />
Safety and Security Management Plans (January 2002), the PMOC must conduct an SSMP review.<br />
Ideally, the format of the SSMP should follow the sections and sub-sections specified in <strong>FTA</strong>’s DRAFT<br />
Guidance and should not include material not specified (such as project description, agency history, etc.).<br />
In evaluating the initial SSMP, the PMOC should use the checklist included in Appendix E of this<br />
guidance. The items are identified by section, beginning with Item 1a, Safety and Security Policy<br />
Statement, and ending with Item 9, FRA Waivers. For each, the PMOC should assess how well the<br />
SSMP meets the requirements. The checklist also requires the PMOC to identify and review any<br />
documents referenced in the SSMP to describe the recipient’s approach to performing specific safety and<br />
security management activities.<br />
Based on the degree of satisfaction with the requirements, the PMOC should follow the rating system<br />
explained in Section 6.1.2 above for rating major capital projects affected by Circular 5800.1. Although<br />
the criteria being rated are somewhat different for the two categories of projects, the rating system is<br />
identical.<br />
6.2.2 SSMP Adherence Review<br />
The PMOC shall conduct an SSMP Adherence Review following the guidance provided in Section 6.1.3<br />
above. The PMOC should apply applicable criteria identified in Section 6.1.3.2 as the SSMP is updated<br />
at various stages of the project while continuing to consider activities described in Chapter II, Section 6,<br />
of Circular 522.A (see Appendix E).<br />
7.0 REPORT, PRESENTATION, RECONCILIATION<br />
7.1 Draft Spot Report and Resolution of Findings<br />
The PMOC should have accumulated findings with respect to the project’s safety and security programs;<br />
their descriptions in the SSMP and supporting plans, policies, and procedures, and the evidence of their<br />
implementation.<br />
OP 22 Safety and Security Management Plan Review<br />
Revision 0, June 2008<br />
Page 10 of 11