• To increase awareness within the transit industry of pitfalls and impediments to achievement<br />

of project goals<br />

• To make changes in <strong>FTA</strong> policies and practices when lessons learned in the field suggest that<br />

such changes may be advisable.<br />

4.0 REFERENCES<br />

The following are the principal, but by no means the only, references to <strong>Federal</strong> legislation, regulation<br />

and guidance with which the PMOC should have a good understanding as related to the Grantee’s<br />

project work being reviewed under this OP: The references in OP 1 apply.<br />

5.0 PROJECT SPONSOR SUBMITTALS<br />

TBD<br />

6.0 SCOPE OF WORK<br />

The PMOC shall document lessons learned in the following manner:<br />

1) At the start of each project phase (preliminary engineering, final design, etc.) the PMOC should<br />

create the framework for the Lessons Learned list. As difficult project events occur, insert<br />

potential lessons into the framework for tracking. As the project develops, review these lessons<br />

with the Grantee and <strong>FTA</strong> staff.<br />

2) Draft a Lessons Learned report, obtain Grantee’s comments and approval on the report, then<br />

submit it to <strong>FTA</strong> for review, approval, and posting to the website.<br />

7.0 REPORT, PRESENTATION, RECONCILIATION<br />

The PMOC shall provide <strong>FTA</strong> with written Lessons Learned reports. If a report content requires more<br />

than one page, a one page executive summary shall be provided. Individual lessons should be<br />

descriptively titled to allow the reader to understand the lesson content through the title alone. The<br />

lessons should be succinctly written. A Lessons Learned report on a particular project may include<br />

one or more lesson, and may or may not include project background information, at the discretion of<br />

the PMOC.<br />

OP 14 Lessons Learned<br />

Revision 0, June 2008<br />

Page 2 of 2