6.1 General Review of Grantee’s Capacity and Capability<br />

At a minimum, the following items are to be reviewed by the PMOC to reach a determination of a<br />

Grantee’s capability and capacity to successfully implement a major <strong>Federal</strong>ly-assisted capital project:<br />

1) Organization, Personnel Qualifications and Experience:<br />

a) The PMOC shall review the complete organization of the Grantee to determine the likelihood<br />

of the project management team to successfully implement the project. Determine whether the<br />

Grantee has an organizational structure conducive to effective and efficient implementation of<br />

the project;<br />

b) Review the assigned and supporting staff qualifications, including but not limited to review of<br />

resumes and personal interviews. Determine whether the Grantee has the appropriately<br />

qualified staff and/or third-party consultants to design the project.<br />

c) Determine if the Grantee staff has experience to deliver the project, given the form of project<br />

delivery method(s) it plans to use, e.g. design/bid/build, design/build, Construction<br />

Management/General Contractor (CM/GC), etc.<br />

d) Analyze whether the Grantee has the physical resources, such as sufficient office space,<br />

equipment and furnishings to effectively and efficiently progress the project.<br />

e) Determine if the Grantee has, or will have, adequate qualified personnel and facilities to<br />

maintain the project along with the Grantee’s existing system.<br />

2) PMP and other readiness documents:<br />

a) Ascertain whether the Grantee has drafted a Project Management Plan (PMP) and associated<br />

readiness documents appropriate for the stage of project development at the time the evaluation<br />

is taking place and, as required by <strong>FTA</strong>, whether the PMP and other readiness documents are<br />

being updated by the Grantee on an ongoing basis.<br />

b) Review the PMP to determine if it defines the objectives of the project and the methods and<br />

resources to be used in meeting those objectives. See the OP for PMP review for more<br />

instruction. Where the current PMP is determined by the PMOC to be adequate for the stage of<br />

project development, the PMOC is to forecast a date when the PMP will require updating.<br />

c) As an example of associated readiness documents: Fleet Management Plan -- If available, the<br />

PMOC shall review the Grantee’s Fleet Management Plan (Bus and/or Rail) to determine that<br />

the Grantee has, or will have, a sufficiently sized fleet to service the project without acquiring a<br />

surplus or reserve fleet that exceeds reasonable requirements. Refer to other OP for instruction<br />

on performing an FMP review.<br />

3) Grantee’s approach to the work, understanding of the work, ability to perform the work<br />

a) Review the adequacy of the Grantee’s methods, policies, and procedures for developing and<br />

updating reasonable and realistic project budgets, cost estimates, and schedules and the control<br />

mechanisms in place to monitor and ensure adherence with said budgets, estimates, and<br />

schedules;<br />

b) Evaluate the Grantee’s ability to<br />

i) identify, analyze, manage and mitigate project risks, especially those involving cost,<br />

technology and schedule risks, in the project;<br />

ii) satisfy <strong>FTA</strong> grant reporting requirements and respond in a timely manner to specific<br />

requests from Congress, the <strong>FTA</strong>, and the PMOC for project-related information;<br />

iii) package, procure and manage third-party contracts in compliance with <strong>FTA</strong> and other<br />

<strong>Federal</strong> requirements;<br />

iv) account for project property and maintenance of project property inventory;<br />

OP 11 Grantee Capacity and Capability Review<br />

Revision 0, June 2008<br />