25.10.2013 Views

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

4.0 REFERENCES<br />

The following are the principal, but by no means the only, references to <strong>Federal</strong> legislation, regulation<br />

and guidance with which the PMOC should have a good understanding as related to the Grantee’s<br />

project work being reviewed under this OP:<br />

4.1 Regulations<br />

• Project Management <strong>Oversight</strong>, 49 C.F.R. Part 633<br />

4.2 Guidance<br />

• Project and Construction Management Guidelines, 2003 Update<br />

5.0 PROJECT SPONSOR SUBMITTALS<br />

Obtain from the Grantee the following:<br />

5.1 Contract Documents – Plans and Specifications and supporting documents as follows:<br />

• Design Criteria and Standards<br />

• Codes and Regulations including those mentioned above<br />

• Relevant Policies<br />

• Operating Rules<br />

• Project Management Plan<br />

• Safety and Security Plan<br />

• Safety Certification<br />

• Quality Assurance/Quality Control Plan<br />

• Risk Assessment Plan<br />

5.2 Project Master Schedule<br />

The schedule for Readiness for Revenue Operations must be integrated into the project master<br />

schedule with time-phased activities showing the inter-dependencies between various activities and<br />

designating project performance milestones. The goal is to schedule the tests in order to avoid<br />

disruption to construction contractor activities and to the grantee’s revenue operations.<br />

Track Access. In order to avoid interfering with or delaying construction, track access must be<br />

coordinated with the contractors and the agency’s operations. This would avoid any disruptions to the<br />

contractors’ progress which could impact the project schedule.<br />

Cutover. One of the most complicated parts of construction involves the "cutover" to an existing<br />

system. The interface point between the existing lines, and the future extensions presents potential for<br />

impacts to existing operations during integrated testing and startup. In developing integrated test<br />

procedures and coordinating the testing, the focus should be on minimizing the impact of integrated<br />

testing during cutover to existing operations. This must be accomplished by proper coordination to<br />

determine windows of time for integrated testing which affects the existing system and to determine<br />

the contractors’ schedules and construction staging plans.<br />

OP 46.5 Readiness for Revenue Operations<br />

Revision 0, June 2008<br />

Page 2 of 5

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!