FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ... FTA Oversight Procedures - Federal Transit Administration - U.S. ...
U.S. DOT Federal Transit Administration TPM-20 Office of Engineering Project Management Oversight Oversight Procedure 46.5 – Readiness for Revenue Operations ______________________________________________________________________________ 1.0 PURPOSE The purpose of this Oversight Procedure is to describe the review, analysis and recommendation procedures and reporting requirements expected by Federal Transit Administration (FTA) from the Project Management Oversight Contractor (PMOC) as regards the Grantee’s readiness for revenue operations as evidenced by completed integrated testing of project components and systems. Through early performance of this procedure, the PMOC can help the Grantee to avoid “11th hour” testing, untimely surfacing of operational problems, and related postponements of the revenue operations date. 2.0 BACKGROUND Completion of the readiness for revenue operations criteria is the ultimate proof that a transit project operates as designed as an integrated whole. Successful achievement of this goal requires expertise, experience, and planning of testing far in advance to avoid impact to construction and the contractually agreed upon revenue operations date. Proper integration and coordination is important so that the testing process is understood by all involved stakeholders including safety personnel, operations, maintenance, engineering, the construction management consultant and the construction contractors. With proper planning, coordination, and comprehensive plans and procedures, the readiness for revenue operations testing can be implemented successfully, and the transit project can be ready for turnover to the transit agency’s operations and maintenance division. It is important that all systems, subsystems, components, equipment, and materials furnished and installed conform to the requirements of the contract documents which generally include plans and specifications. Integrated testing of systems includes such elements as track and associated trackwork; train control systems; signal systems; communications; traction power systems including substations, third rails, overhead catenary systems; vehicles; grade crossing protection systems including traffic signal timing; fare collection systems; and stations. 3.0 OBJECTIVES The objectives are to assess whether: • All systems, subsystems, components, equipment, and materials furnished and installed conform to the requirements of the contract documents • The entire transit system, with all interfaces, operates as indicated in the contract documents as an integrated whole and is capable of functioning effectively to provided dependable service. OP 46.5 Readiness for Revenue Operations Revision 0, June 2008 Page 1 of 5
4.0 REFERENCES The following are the principal, but by no means the only, references to Federal legislation, regulation and guidance with which the PMOC should have a good understanding as related to the Grantee’s project work being reviewed under this OP: 4.1 Regulations • Project Management Oversight, 49 C.F.R. Part 633 4.2 Guidance • Project and Construction Management Guidelines, 2003 Update 5.0 PROJECT SPONSOR SUBMITTALS Obtain from the Grantee the following: 5.1 Contract Documents – Plans and Specifications and supporting documents as follows: • Design Criteria and Standards • Codes and Regulations including those mentioned above • Relevant Policies • Operating Rules • Project Management Plan • Safety and Security Plan • Safety Certification • Quality Assurance/Quality Control Plan • Risk Assessment Plan 5.2 Project Master Schedule The schedule for Readiness for Revenue Operations must be integrated into the project master schedule with time-phased activities showing the inter-dependencies between various activities and designating project performance milestones. The goal is to schedule the tests in order to avoid disruption to construction contractor activities and to the grantee’s revenue operations. Track Access. In order to avoid interfering with or delaying construction, track access must be coordinated with the contractors and the agency’s operations. This would avoid any disruptions to the contractors’ progress which could impact the project schedule. Cutover. One of the most complicated parts of construction involves the "cutover" to an existing system. The interface point between the existing lines, and the future extensions presents potential for impacts to existing operations during integrated testing and startup. In developing integrated test procedures and coordinating the testing, the focus should be on minimizing the impact of integrated testing during cutover to existing operations. This must be accomplished by proper coordination to determine windows of time for integrated testing which affects the existing system and to determine the contractors’ schedules and construction staging plans. OP 46.5 Readiness for Revenue Operations Revision 0, June 2008 Page 2 of 5
- Page 230 and 231: milestones, the value of expected m
- Page 232 and 233: U.S. DOT Federal Transit Administra
- Page 234 and 235: 4.2 Guidance coordination of platfo
- Page 236 and 237: communicate with the vehicle manufa
- Page 238 and 239: APPENDIX A FTA Request for Informat
- Page 240 and 241: APPENDIX B OP 41 ADA Review - Level
- Page 242 and 243: 4.1 Legislative • The Safe, Accou
- Page 244 and 245: 4) Cost estimate in year-of-expendi
- Page 246 and 247: U.S. DOT Federal Transit Administra
- Page 248 and 249: • Project Schedule (Master Schedu
- Page 250 and 251: d) Assessed safety and security iss
- Page 252 and 253: U.S. DOT Federal Transit Administra
- Page 254 and 255: • Interim Guidance on Design-Buil
- Page 256 and 257: (3) Appropriateness of the proposed
- Page 258 and 259: 7) Project Schedule The PMOC should
- Page 260 and 261: U.S. DOT Federal Transit Administra
- Page 262 and 263: 2) The Grantee’s program for adva
- Page 264 and 265: 2. Identify all apparent discrepanc
- Page 266 and 267: • The PMOC shall assess whether t
- Page 268 and 269: to FD phase of the project, should
- Page 270 and 271: Table 1, continued: Expected Attrib
- Page 272 and 273: • Real Estate Acquisition Managem
- Page 274 and 275: U.S. DOT Federal Transit Administra
- Page 276 and 277: performed Quality assurance records
- Page 278 and 279: plan that ensures the necessary qua
- Page 282 and 283: 5.3 Systems/Facilities Integration
- Page 284: 6.2 Successful completion and recor
U.S. DOT <strong>Federal</strong> <strong>Transit</strong> <strong>Administration</strong><br />
TPM-20 Office of Engineering<br />
Project Management <strong>Oversight</strong><br />
<strong>Oversight</strong> Procedure 46.5 – Readiness for Revenue Operations<br />
______________________________________________________________________________<br />
1.0 PURPOSE<br />
The purpose of this <strong>Oversight</strong> Procedure is to describe the review, analysis and recommendation<br />
procedures and reporting requirements expected by <strong>Federal</strong> <strong>Transit</strong> <strong>Administration</strong> (<strong>FTA</strong>) from the<br />
Project Management <strong>Oversight</strong> Contractor (PMOC) as regards the Grantee’s readiness for revenue<br />
operations as evidenced by completed integrated testing of project components and systems. Through<br />
early performance of this procedure, the PMOC can help the Grantee to avoid “11th hour” testing,<br />
untimely surfacing of operational problems, and related postponements of the revenue operations date.<br />
2.0 BACKGROUND<br />
Completion of the readiness for revenue operations criteria is the ultimate proof that a transit project<br />
operates as designed as an integrated whole. Successful achievement of this goal requires expertise,<br />
experience, and planning of testing far in advance to avoid impact to construction and the contractually<br />
agreed upon revenue operations date.<br />
Proper integration and coordination is important so that the testing process is understood by all<br />
involved stakeholders including safety personnel, operations, maintenance, engineering, the<br />
construction management consultant and the construction contractors. With proper planning,<br />
coordination, and comprehensive plans and procedures, the readiness for revenue operations testing<br />
can be implemented successfully, and the transit project can be ready for turnover to the transit<br />
agency’s operations and maintenance division. It is important that all systems, subsystems,<br />
components, equipment, and materials furnished and installed conform to the requirements of the<br />
contract documents which generally include plans and specifications. Integrated testing of systems<br />
includes such elements as track and associated trackwork; train control systems; signal systems;<br />
communications; traction power systems including substations, third rails, overhead catenary systems;<br />
vehicles; grade crossing protection systems including traffic signal timing; fare collection systems; and<br />
stations.<br />
3.0 OBJECTIVES<br />
The objectives are to assess whether:<br />
• All systems, subsystems, components, equipment, and materials furnished and installed<br />
conform to the requirements of the contract documents<br />
• The entire transit system, with all interfaces, operates as indicated in the contract documents<br />
as an integrated whole and is capable of functioning effectively to provided dependable<br />
service.<br />
OP 46.5 Readiness for Revenue Operations<br />
Revision 0, June 2008<br />
Page 1 of 5