U.S. DOT <strong>Federal</strong> <strong>Transit</strong> <strong>Administration</strong><br />

TPM-20 Office of Engineering<br />

Project Management <strong>Oversight</strong><br />

<strong>Oversight</strong> Procedure 11 - Grantee Capacity and Capability Review<br />

______________________________________________________________________________<br />

1.0 PURPOSE<br />

The purpose of this <strong>Oversight</strong> Procedure is to describe the review, analysis, and recommendation<br />

procedures and reporting requirements expected by <strong>Federal</strong> <strong>Transit</strong> <strong>Administration</strong> (<strong>FTA</strong>) from the<br />

Project Management <strong>Oversight</strong> Contractor (PMOC) with regard to the Grantee’s management,<br />

organization, and technical capability to effectively and efficiently plan, develop, and implement a<br />

<strong>Federal</strong>ly-assisted capital project.<br />

2.0 BACKGROUND<br />

The PMOC shall review a Grantee’s technical capability and capacity to efficiently and effectively<br />

develop a <strong>Federal</strong>ly-assisted project for implementation by evaluating the qualifications and<br />

organizational structure of the Grantee as well as its implementation methods, policies, and procedures.<br />

Particular attention needs to be given to the Grantee’s abilities, resources, and organizational structure,<br />

either through its own staff or qualified third-party consultants, to develop and implement project plans<br />

as well as identify and manage project cost and schedule risks, real estate acquisition (as applicable),<br />

safety and security requirements, quality assurance and quality control, and other issues of <strong>Federal</strong><br />

concern. The results of this evaluation shall serve the <strong>FTA</strong> in programmatic decisions and<br />

determinations regarding whether the Grantee has demonstrated readiness to receive <strong>Federal</strong> funds at<br />

the various project stages.<br />

3.0 OBJECTIVES<br />

Perform an initial evaluation of a Grantee’s capacity and capability to successfully implement a major<br />

<strong>Federal</strong>ly-assisted capital project, and perform subsequent partial or supplemental evaluations of a<br />

Grantee’s continued capacity and capability during the implementation of a project. The evaluations<br />

should cover the following:<br />

1) Organization, Personnel Qualifications and Experience<br />

2) Project Management Planning Documents<br />

3) Grantee’s approach to the work, understanding of the work, ability to perform the work<br />

4.0 REFERENCES<br />

The following are the principal, but by no means the only, references to <strong>Federal</strong> legislation, regulation<br />

and guidance with which the PMOC should have a good understanding as related to the Grantee’s<br />

project work being reviewed under this OP:<br />

4.1 Regulations<br />

• 49 CFR Part 633, Project Management <strong>Oversight</strong>, dated 1989;<br />

OP 11 Grantee Capacity and Capability Review<br />

Revision 0, June 2008<br />

Page 1 of 4