such, the spot report will largely summarize information from previously reviews of project plans and<br />

analysis, modified as necessary to reflect any changes that occurred after the earlier review.<br />

The following is a preliminary table of contents for the spot report<br />

List of Acronyms<br />

Executive Summary<br />

1. Introduction / Objectives<br />

2. Overview<br />

a. Background<br />

b. Project Scope (Facilities and Systems) with Map<br />

c. Operations (Hours, Fleet, Ridership)<br />

d. Design Status<br />

e. Contract Packaging Plan<br />

f. Financing Plan<br />

3. FFGA Supporting Document Review<br />

a. Project Management Plan<br />

b. Bus and Rail Fleet Management Plans<br />

c. Value Engineering<br />

d. Final Design<br />

e. Quality Assurance Program Plan<br />

f. Document Control Plan<br />

g. Real Estate Acquisition Management Plan<br />

h. Railroad Agreements<br />

i. Third Party Agreements<br />

j. Private Utility Agreements<br />

k. Environmental Permits<br />

l. Safety and Security Management Plan<br />

m. Risk Assessment and Mitigation<br />

4. Cost Estimate and Baseline Budget Review<br />

a. Cost Estimate Assessment<br />

b. Baseline Schedule Assessment<br />

5. Conclusions / Recommendation<br />

OP 46.3 Readiness to Execute or Amend FFGA<br />

Revision 0, June 2008<br />