Table 1, continued: Expected Attributes of Project Design Plans<br />
(Completion of PE/Approval to Enter Final Design)<br />
Design Activity Type/Level of Design Detail (for Inclusion in PE Planset)<br />
Maintenance Facility Overall site plan (existing and proposed conditions)<br />
Grading plans and site cross sections<br />
Yard/lot layout, with typical sections<br />
Access (roadway, parking) plans<br />
Utility plans<br />
Demolition, landscaping and irrigation, drainage plans, as appropriate<br />
Building/facilities plans, including footprint, basic floor plans (functional space layouts), sections<br />
Foundation and foundation section plans<br />
Safety and security, fire protection plans<br />
Basic equipment lists<br />
Traction power (OCS, substation locations) plans for rail systems<br />
Other Urban design/general landcaping features<br />
Architectural elements (general concepts/objectives)<br />
Schedule Activity Type/Level of Schedule Information<br />
Final Design All major final design activities indicated.<br />
For each design discipline (civil, structural, systems, other) detail provided on scope/main tasks<br />
All early permits identified as milestone or more detailed activity if possible<br />
Carryover/incomplete activities from PE identified<br />
Milestones for 60%, 90% and 100% (or similar) percent complete indicated<br />
--Logic ties to predecessor activities shown<br />
--Required reviews and approvals indicated<br />
Logic ties between other major activities shown<br />
Advertise and Bid Construction packages indicated; single activity for advertise/bid acceptable<br />
Logic ties provided from design to advertise/bid and from advertise/bid to construction<br />
Construction Outline level of detail, including<br />
--Each construction package indicated<br />
--Five to 15 activities per package, depending upon size<br />
Utilities Outline level of detail, including<br />
--Which utilities affected by project<br />
--Estimated timeframe/duration of utility work<br />
--Design detail included in FD section of schedule<br />
Real Estate Outline level of detail, including<br />
--Several basic activities included for each construction package<br />
--Logic ties shown from design to real estate and from real estate to construction<br />
Final Testing and<br />
Startup<br />
Table 2: Expected Attributes of Project Schedule<br />
(Completion of PE/Approval to Enter Final Design)<br />
Single activity indicating duration and predecessor logic acceptable<br />
For phased openings, preliminary detail (e.g., milestones) provided<br />
Placeholder for safety certification acceptable<br />
Additional detail would be added in other areas as project proceeds until schedule is complete.<br />
OP 46.2 Readiness to Enter Final Design<br />
Revision 0, June 2008<br />
Page 11 of 11