Table 1, continued: Expected Attributes of Project Design Plans<br />

(Completion of PE/Approval to Enter Final Design)<br />

Design Activity Type/Level of Design Detail (for Inclusion in PE Planset)<br />

Maintenance Facility Overall site plan (existing and proposed conditions)<br />

Grading plans and site cross sections<br />

Yard/lot layout, with typical sections<br />

Access (roadway, parking) plans<br />

Utility plans<br />

Demolition, landscaping and irrigation, drainage plans, as appropriate<br />

Building/facilities plans, including footprint, basic floor plans (functional space layouts), sections<br />

Foundation and foundation section plans<br />

Safety and security, fire protection plans<br />

Basic equipment lists<br />

Traction power (OCS, substation locations) plans for rail systems<br />

Other Urban design/general landcaping features<br />

Architectural elements (general concepts/objectives)<br />

Schedule Activity Type/Level of Schedule Information<br />

Final Design All major final design activities indicated.<br />

For each design discipline (civil, structural, systems, other) detail provided on scope/main tasks<br />

All early permits identified as milestone or more detailed activity if possible<br />

Carryover/incomplete activities from PE identified<br />

Milestones for 60%, 90% and 100% (or similar) percent complete indicated<br />

--Logic ties to predecessor activities shown<br />

--Required reviews and approvals indicated<br />

Logic ties between other major activities shown<br />

Advertise and Bid Construction packages indicated; single activity for advertise/bid acceptable<br />

Logic ties provided from design to advertise/bid and from advertise/bid to construction<br />

Construction Outline level of detail, including<br />

--Each construction package indicated<br />

--Five to 15 activities per package, depending upon size<br />

Utilities Outline level of detail, including<br />

--Which utilities affected by project<br />

--Estimated timeframe/duration of utility work<br />

--Design detail included in FD section of schedule<br />

Real Estate Outline level of detail, including<br />

--Several basic activities included for each construction package<br />

--Logic ties shown from design to real estate and from real estate to construction<br />

Final Testing and<br />

Startup<br />

Table 2: Expected Attributes of Project Schedule<br />

(Completion of PE/Approval to Enter Final Design)<br />

Single activity indicating duration and predecessor logic acceptable<br />

For phased openings, preliminary detail (e.g., milestones) provided<br />

Placeholder for safety certification acceptable<br />

Additional detail would be added in other areas as project proceeds until schedule is complete.<br />

OP 46.2 Readiness to Enter Final Design<br />

Revision 0, June 2008<br />

Page 11 of 11