Table 1: Expected Attributes of Project Design Plans<br />

(Completion of PE/Approval to Enter Final Design)<br />

Design Activity Type/Level of Design Detail (for Inclusion in PE Planset)<br />

Design Criteria Project sponsor accepted design standards and performance requirements<br />

Photogrammetry Digitized aerial photogrammetry (aerial photo background; planimetric and topographic mapping)<br />

Renderings Photosimulations and/or schematic renderings<br />

Guideway Plans Guideway (track/busway/transitway) general notes, standard abbreviations and symbols<br />

Guideway key map; horizontal and vertical controls<br />

Guideway alignment geometry (plan and profile)<br />

Guideway curve data (table and/ included in drawings)<br />

Load diagrams for structures (e.g., aerial guideway)<br />

Typical sections<br />

Guideway drainage plans, including key map, notes and symbols<br />

General layouts of (each) grade crossings<br />

Maintenance of traffic for special situations<br />

Pedestrian crossings<br />

Guideway Structures Bridge and wall nomenclature, symbols and abbreviations, and general notes<br />

Bridge and wall general plans<br />

Bridge foundation, abutment, bent plans, and deck plans<br />

Retaining walls, including typical wall sections<br />

Tunnel layout plans<br />

Tunnel structural plans and typical sections<br />

Tunnel excavation plans, approach wall plans and sections<br />

Other tunnel detail optional: emergency walkway, groundwater control and tunnel drainage,<br />

safety and security, fire protection, communications, lighting, ventilation<br />

Stations and Finishes General information, including notes and legend<br />

Station layout plans<br />

Platform details<br />

Grading and drainage plans<br />

Utilities, landscaping<br />

Access and parking plans, including paving<br />

Aerial station plans showing basic structural and architectural elements, including platform details<br />

Tunnel (underground) station plans showing structures and basic architectural details, including<br />

platform details<br />

Right of Way Plans Right of way limits<br />

Parcel/property acquisitions and easements, if known<br />

Roadways Key map showing roadway plan with signalized and other intersections<br />

Roadway plans and profiles<br />

Typical sections<br />

Drainage plans<br />

Signing plans<br />

Intersection traffic signal plans<br />

Utility Plans Utilities key map, list of owners, symbols, and notes<br />

Utilities plans<br />

Environmental Mitigation Plans On-site mitigation plans<br />

Systems Traction power plans, including location of substations and feeds; OCS layouts, as relevant<br />

Train/vehicle control plans, including schematic guideway layout (e.g., circuits/block diagrams)<br />

Operations control center plan, including basic layout and space allocations<br />

Communications plans, including equipment locations, and provisions for station message signs,<br />

phones, cameras, other<br />

OP 46.2 Readiness to Enter Final Design<br />

Revision 0, June 2008<br />

Page 10 of 11