• The PMOC shall assess whether the estimate includes sufficient detail to establish a reasonably<br />
accurate cost for project development through construction and start-up. If based on<br />
quantities/activities and unit costs, are the quantities/activities adequately defined? What prices are<br />
lump sums versus based on market research or quotes from potential suppliers/vendors?<br />
• Allocated and unallocated contingencies shall be identified and a professional judgment offered as<br />
to the adequacy of contingencies, given project risks, complexity, and other factors.<br />
OP 33 Capital Cost Estimate describes the procedures for evaluating the reasonableness and accuracy<br />
of capital cost estimates. The results of this review, if performed commensurate with the completion of<br />
PE/Entry to FD phase of the project, should be incorporated into the OP 46.2 assessment of readiness<br />
to enter final design.<br />
6.3 Technical Capacity and Capability and Other Readiness Reviews<br />
• The PMOC shall meet with the Grantee to review the grantee’s latest approved PMP.<br />
o The PMOC shall compare the PMP to the grantee’s current and proposed organizational<br />
structure.<br />
o The Grantee shall provide the PMOC with the agency's organization chart and job<br />
descriptions for the key positions in responsible charge of the final design process.<br />
o The PMOC shall evaluate whether sufficient breadth and depth are contained in the<br />
proposed organization to successfully execute final design.<br />
o The PMOC shall evaluate technical capacity based on the complexity of the scope of the<br />
project, detail/number of activities and activity interrelations described in the project master<br />
schedule, the size of the project budget and also the contracting approach to the project.<br />
o Additionally, the PMOC will consider other resources available to the project, including<br />
from project partners, consultant support, and other non-sponsor agency resources.<br />
PMP review procedures are described in OP No. 20 Project Management Plan Review. The results<br />
of this review, if performed commensurate with the completion of PE/Entry to FD phase of the<br />
project, should be incorporated into this analysis of Grantee technical capacity and capability.<br />
• The PMOC shall examine the Quality Assurance/Quality Control Plan (QAP) and verify that it is<br />
in compliance with <strong>FTA</strong> guidance documents, including Project and Construction Management<br />
Guidelines and <strong>FTA</strong> QA/QC Guidelines (latest updates). At entry to final design, the QAP shall<br />
fully address all elements governing project activities through the design phase. It should also<br />
contain, at least in outline form and to the level of detail possible, information relative to the<br />
upcoming construction phase.<br />
QAP review procedures are defined in OP No. 21, Quality Assurance/Quality Control Program<br />
Reviews. The results of this review, if performed commensurate with the completion of PE/Entry<br />
to FD phase of the project, should be incorporated into this analysis of Grantee technical capacity<br />
and capability.<br />
• The PMOC shall examine the Safety and Security Management Plan (SSMP) and verify that it is in<br />
compliance with <strong>FTA</strong> guidance as provided in Circular C5800.1.<br />
SSMP review procedures are defined in OP No. 22, Safety and Security Management Plan<br />
Reviews. The results of this review, if performed commensurate with the completion of PE/Entry<br />
to FD phase of the project, should be incorporated into this analysis of Grantee technical capacity<br />
and capability.<br />
OP 46.2 Readiness to Enter Final Design<br />
Revision 0, June 2008<br />
Page 7 of 11