FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
performance of various aspects of the project, including user benefits as opposed to capital and<br />
operating costs, local financial commitment, land use and economic development effects, and other<br />
factors. Section 5309(d)(1)(B)(ii) directs <strong>FTA</strong> to consider proposed New Starts projects for Full<br />
Funding Grant Agreements (FFGA) and proposed Small Starts for Project Construction Grant<br />
Agreements (PCGA) only if they receive a Medium, Medium-High, or High overall project rating<br />
(See:http://www.fta.dot.gov/planning/newstarts/planning_environment_2620.html).<br />
2.2 Preliminary Engineering Design Requirements<br />
Progress towards completing the project design and the corresponding cost estimate and schedule to<br />
build the project must be satisfactory. As noted, PE generally requires design detail to 30 percent and<br />
capital cost estimate detail based upon (a) quantities of work established in the plans and (b) for all<br />
other costs (vehicles, equipment, land/right-of-way, administrative costs, consultant and other support,<br />
finance costs, etc.) a reasonable level of line item detail. The master schedule should include sufficient<br />
detail to identify all significant activities, their durations, and logical ties to other activities. Section 6.0<br />
Scope of Work provides direction for determining whether the level of detail in the PE plans, cost<br />
estimate and schedule is sufficient as well as what other information is required to demonstrate<br />
technical readiness to enter final design.<br />
2.3 Grantee Readiness: Technical Capacity and Capability<br />
Whether the Grantee has the necessary management approach and organizational structure, internal<br />
and external controls, and other resources available to administer a project—technical capacity and<br />
capability—is another important aspect of readiness to enter final design. The procedures for making<br />
these assessments are established in other guidance (see 4.0 References). The Grantee should<br />
document its program for project management in a current Project Management Plan for at least the<br />
design phase of project development (the PMP would incorporate provisions for construction as that<br />
phase approaches).<br />
At the conclusion of PE a project is likely to be subject to a formalized risk assessment that will<br />
evaluate whether the grantee has incorporated risk-based methods into its approach to project<br />
management. <strong>FTA</strong> guidelines also call for the Grantee to evaluate the project design through a formal,<br />
independent value engineering process during or at the close of PE. Both the risk assessment and value<br />
engineering processes are to be incorporated in the PMP, which describes their purpose and objectives,<br />
summarizes findings, and presents the action plan resulting from each process (e.g., Project Risk<br />
Management Plan for a risk assessment). The assessment of readiness to enter final design conducted<br />
under OP 46.2 incorporates findings of the risk assessment and value engineering programs.<br />
3.0 OBJECTIVES<br />
<strong>FTA</strong> desires the PMOC’s professional and well reasoned findings and recommendations regarding the<br />
readiness of the Grantee to enter and complete the final design phase. Findings and recommendations<br />
shall pertain to:<br />
1) The completeness, quality, and accuracy of engineering design, the project schedule, and the<br />
project capital cost estimate at the conclusion of PE.<br />
OP 46.2 Readiness to Enter Final Design<br />
Revision 0, June 2008<br />
Page 2 of 11