25.10.2013 Views

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Project Background Project descriptions and data shall be consistent with the Monitoring report<br />

guidance, current monitoring report and the most recent <strong>FTA</strong> New Start profile. Notwithstanding<br />

the foregoing, the work order manager may direct the contractor to use an identifiable draft version<br />

of these materials. Ridership shall include peak hour ridership data. Sub‐sectioning shall also<br />

include Guideway Components, Project Delivery Method, proposed Contract Packaging Strategy<br />

and, as applicable, Master Planning for the Corridor.<br />

Methodology This purpose of this section is to describe the PMOC’s methodology used to deliver<br />

the sampling plan, risk management products with separate sections for risk assessment, and<br />

mitigation forecasts. This shall present, discuss, and thoroughly demonstrate the contractor’s<br />

approach to developing the 10th percentile estimates. Subsection as appropriate, divided into<br />

subtasks.<br />

Risk Identification for SCC/Baseline Cost Estimate Units The purpose of this section is to<br />

present a synopsis of the capacity, scope, cost, schedule and contingency findings in other PGs.<br />

Present the cost estimate adjustments and selection of beta values for the Category Cost Risk<br />

Assessment; cost estimate adjustments shall identify whether there are mitigatable components.<br />

The Contractor shall present detailed data and analysis in a separate appendix as necessary in<br />

order to maintain readability of the report.<br />

All recommendations shall be adequately supported with analysis and rationales as well as<br />

identifying the current project status and timeframe of the baseline. The analysis shall be consistent<br />

with the Risk Mitigation structure and segregate risks into requirements, design, market and<br />

construction risk sub sections.<br />

A Risk Register shall be delivered as a separate appendix in the form of Excel or Access data tables.<br />

Risk Management Baseline The purpose of this section is to present the contractor’s initial<br />

Project Cost Risk Assessment, for comparison, throughout the future phases of the project.<br />

Risk Mitigation Framework The purpose of this section is to present the contractor’s<br />

recommendation for specific risk mitigation/transfer/sharing efforts by the grantee to reduce the<br />

perceived risks and potential variability of costs through each of the project milestones. The<br />

PMOC’s narrative should allow <strong>FTA</strong> management and the Grantee to maintain focus upon these risk<br />

mitigation/transfer/sharing efforts as the means to maintain the baseline cost estimate and avoid<br />

the potential cost escalation from these potential project risks.<br />

A subsection shall be included for each Mitigation Milestone that addresses:<br />

• Basis for Project Risk Status forecast.<br />

• Requirements risk status, Design risk status, Market/bid Risk status, Geotechnical/Utility<br />

Construction Risk status, Mid Range Coordination Construction Risk status and Start up<br />

risk.<br />

• Mitigation Objectives<br />

• The PMOC shall present its model‐based simulation of grantee implementation (expected<br />

outcomes achieved) of all identified mitigation activities/deliverables at each of the<br />

OP 40 Risk Assessment and Mitigation Review<br />

Revision 0, June 2008<br />

Page 14 of 16

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!