FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
6.6.4 Secondary Risk Mitigation Recommendations<br />
The PMOC shall develop recommendations for activities to accomplish Secondary Risk Mitigation.<br />
These recommendations shall include both the targeted magnitude of the cost or time savings<br />
expected, as well as a description of the scope, deliverables, and outcomes of the activity. The<br />
contractor will also recommend progress‐reporting intervals for tracking the performance and<br />
management of such mitigation capacities; as well as any integration with the Grantee’s overall<br />
program schedule and resource loading. All material assumptions shall be identified along with<br />
their rationales. Such recommendations are to be established as distinct from any concurrent value<br />
engineering activities.<br />
Value Engineering (VE) is a formal, systematic, multi‐disciplined process designed to optimize the<br />
value of each dollar spent. The objective of VE is to satisfy all required functions at the lowest total<br />
costs (capital, operating and maintenance) over the life of the project consistent with the<br />
requirements of performance, reliability, maintainability, safety and esthetics. The VE process<br />
generates a list of alternative methods for performing the required functions involved in the<br />
targeted areas of the design represented by any given scope element that when taken as an<br />
aggregate, are likely to achieve a project cost‐reduction objective. The result is change in the<br />
physical or technical aspects of project. VE recommendations if accepted by the Grantee are<br />
implemented on a non‐contingent basis.<br />
Secondary Mitigation is also a formal, systematic, multi‐disciplined process but it is designed to<br />
achieve a cost‐reduction objective in targeted areas of the design, construction general conditions,<br />
etc. with or without a material reduction in transit capacity, level of service, or revenue vehicles.<br />
Secondary Mitigation and Value Engineering both can result in reductions to Project Scope, transit<br />
capacity, level of service, etc. and thereby Project Cost (and Project Schedule as applicable).<br />
Secondary Mitigation is reduction(s) in project scope that might, in certain circumstances, merit<br />
reinstatement back into the project, i.e. “mitigation recapture”. Secondary Mitigation is<br />
fundamentally different than Value Engineering.<br />
Mitigation Targets are amounts of secondary mitigation that are recommended to be developed<br />
on a phase‐by‐phase basis. These targets are developed upon the result of the Cost Risk<br />
Assessment developed in 6.2.2. The Mitigation Target for a given phase is a percentage of the<br />
difference between the project budget and either: 1) the 90 th percentile forecast at each of the<br />
Project Milestones (see 6.2.2.1), or 2) an adjusted target that includes contingency values<br />
established through OP‐35. Table 2 provides the initial recommendation for percentages to apply<br />
to the difference (or “gap”) between the budget and 90 th percentile forecast. The PMOC may, with<br />
the <strong>FTA</strong> work order manager’s approval, modify these targets based upon overlapping Grantee<br />
milestones, or develop additional targets due to additional milestones lying between these targets.<br />
Table 2 - Mitigation Target Percentages<br />
Milestone Target<br />
Entry in Preliminary Engineering 10%<br />
Entry into Final Design 30%<br />
FFGA award 50%<br />
40% bid 60%<br />
20% construction 70%<br />
50% construction 80%<br />
OP 40 Risk Assessment and Mitigation Review<br />
Revision 0, June 2008<br />
Page 12 of 16