etween risk reduction and risk acceptance typically occurs at the point where all market risk has<br />
been mitigated, or early construction risk (geotechnical/utility) has also been mitigated, whichever<br />
occurs later. Prior to this “break point”, unless otherwise provided for in a project strategy plan,<br />
triggered mitigation is the first line of defense in order to preserve and the minimum contingency<br />
balance must be met in order to provide sufficient funds for the completion of the project, or<br />
revenue operations consistent with Project Strategy parameters defined in later deliverables.<br />
6.6.2 Primary Cost Risk Mitigation Recommendations<br />
The PMOC shall develop a unified list of cost mitigation activities, including scope, deliverables, and<br />
outcomes, based upon products previously developed through this OP‐40 and other OPs. This list<br />
shall be entitled “Primary Mitigation Deliverables and Outcomes”. This list will serve as a means to<br />
provide recommendations and to monitor the reduction of project cost risk. The PMOC’s evaluation<br />
of these Grantee’s activities as recommended shall be performed as part of 6.7 Specialized Risk<br />
Management products.<br />
6.6.3 Primary Schedule Risk Mitigation Recommendations<br />
The PMOC shall develop a unified list of schedule mitigation activities, including scope, deliverables,<br />
and outcomes, based upon products previously developed through this OP‐40 and other OPs. This<br />
list shall be integrated with the list entitled “Primary Mitigation Deliverables and Outcomes”,<br />
developed in 6.6.2, above. This list serves as means to provide recommendations and monitor<br />
schedule risk to the project. The PMOC’s evaluation of the Grantee’s activities as recommended<br />
shall be performed as part of 6.7 Specialized Risk Management products.<br />
Schedule risk mitigation recommendations shall recognize that schedule risk is focused on the<br />
homogeneity and stability of the project critical path. A critical path is homogeneous when its<br />
activities are mapped out using a histogram and demonstrate a mode and mean activity duration<br />
that is within 10% of each other. A critical path is ideally stable when all delays on other paths<br />
consume their path float but do not result in a project delay and no event has consumed all float,<br />
becoming critical.<br />
Schedule risk mitigation recommendations should specifically treat both critical path and non‐<br />
critical path activities. Frequent changes in the configuration of the project critical path are<br />
disruptive and degrade the grantee’s ability to efficiently and effectively implement the project.<br />
The role of schedule mitigation is to protect the critical path from non‐critical path activities<br />
becoming critical themselves.<br />
The primary objective of schedule risk management is keeping a necessary amount of path float<br />
between the project critical path and all of its intersecting paths, i.e. to “buffer” the critical path and<br />
thus preserve its stability. The secondary objective of schedule risk management is to keep<br />
technical risks off of the project critical path, or minimize their duration if they are critical path<br />
activities.<br />
High risk project work elements are to be executed as early as possible in the project schedule such<br />
that their negative outcomes can be mitigated by triggered mitigation and not by the application of<br />
project contingency.<br />
OP 40 Risk Assessment and Mitigation Review<br />
Revision 0, June 2008<br />