FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Example events that may incur secondary mitigation include construction bids that are significantly<br />
over the estimate, or unexpected geotechnical hazards that are encountered, etc., such that the<br />
change is likely to cause a significant over‐budget condition. Such “triggered” mitigation enables<br />
the Grantee to make cost reductions in a planned and orderly process and preserves contingencies<br />
for use later in the project.<br />
Tertiary Mitigation consists of adjustment to the project budget by means of supplementing or<br />
“recharging” the project funds. Tertiary mitigation generally is a last‐resort reaction to incurred<br />
risk, occurring only when primary and secondary mitigation has been exhausted. Tertiary<br />
mitigation should only be recommended upon consultation with and approval of the <strong>FTA</strong>. Such<br />
“recharge” mitigation enables the grantee to take further steps in a planned and orderly process<br />
and ensures secondary mitigation capacity meets minimum requirements in the next phase.<br />
6.6.1.3 Mitigation Types<br />
The PMOC shall organize risk mitigation recommendations into four categories—Risk Transfer,<br />
Risk Avoidance, Risk Reduction, or Risk Acceptance.<br />
Risk Transfer occurs when the consequences resulting from a risk event become the liability of a<br />
party other than the Grantee; this may include a partial transfer (or risk sharing). The PMOC shall<br />
clearly identify those risks that can be shared with or transferred to a third party such as a<br />
contractor, consultant, or other governmental organization in the form of contract requirements,<br />
warranties, or insurance policies, etc. The recommendation may also be to reallocate scope in such<br />
a manner as to transfer risks to scope elements or contract packages that are better suited to<br />
mitigate risk.<br />
Risk Avoidance is available when a project element that is associated with certain potential risk<br />
may be alternatively delivered through a less‐risky process or design, or may be eliminated<br />
altogether. The PMOC shall clearly identify those risks that can be avoided or eliminated.<br />
Risk Reduction is a planned action that will either reduce the consequence or the likelihood of a<br />
risk event. The PMOC shall clearly identify the root cause of the risk event, how the root cause will<br />
be reduced by implementing the PMOC’s recommendation, and who the PMOC recommends within<br />
the Grantee organization or project team to carry out the risk mitigation scope element. The PMOC<br />
will also recommend progress‐reporting intervals for tracking the performance of mitigation<br />
measures as well as any integration with the Grantee’s overall program schedule and resource<br />
loading. All material assumptions shall be identified along with their rationales.<br />
Risk Acceptance results from the recognition, in the PMOC’s opinion, that further reduction of a<br />
particular risk would only come at the expense of unacceptable scope reduction or cost increase,<br />
etc. The PMOC shall clearly identify those risks that it recommends the Grantee accept as inherent<br />
to the project. Risk Acceptance often involves the consumption of project contingency funds,<br />
project schedule float, or an increase in either project budget or schedule.<br />
When providing recommendations, the PMOC shall only suggest Risk Acceptance when neither Risk<br />
Avoidance, Risk Reduction, nor Risk Transfer is available. However, PMOC recommendations shall<br />
recognize that there is a point in the implementation of the Grantee’s project (“break point”) where<br />
mitigation becomes increasingly difficult to effect and beyond which Risk Acceptance through the<br />
use of project contingency funds is the only effective means to treat project risk. This “break point”<br />
OP 40 Risk Assessment and Mitigation Review<br />
Revision 0, June 2008<br />
Page 10 of 16