25.10.2013 Views

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Example events that may incur secondary mitigation include construction bids that are significantly<br />

over the estimate, or unexpected geotechnical hazards that are encountered, etc., such that the<br />

change is likely to cause a significant over‐budget condition. Such “triggered” mitigation enables<br />

the Grantee to make cost reductions in a planned and orderly process and preserves contingencies<br />

for use later in the project.<br />

Tertiary Mitigation consists of adjustment to the project budget by means of supplementing or<br />

“recharging” the project funds. Tertiary mitigation generally is a last‐resort reaction to incurred<br />

risk, occurring only when primary and secondary mitigation has been exhausted. Tertiary<br />

mitigation should only be recommended upon consultation with and approval of the <strong>FTA</strong>. Such<br />

“recharge” mitigation enables the grantee to take further steps in a planned and orderly process<br />

and ensures secondary mitigation capacity meets minimum requirements in the next phase.<br />

6.6.1.3 Mitigation Types<br />

The PMOC shall organize risk mitigation recommendations into four categories—Risk Transfer,<br />

Risk Avoidance, Risk Reduction, or Risk Acceptance.<br />

Risk Transfer occurs when the consequences resulting from a risk event become the liability of a<br />

party other than the Grantee; this may include a partial transfer (or risk sharing). The PMOC shall<br />

clearly identify those risks that can be shared with or transferred to a third party such as a<br />

contractor, consultant, or other governmental organization in the form of contract requirements,<br />

warranties, or insurance policies, etc. The recommendation may also be to reallocate scope in such<br />

a manner as to transfer risks to scope elements or contract packages that are better suited to<br />

mitigate risk.<br />

Risk Avoidance is available when a project element that is associated with certain potential risk<br />

may be alternatively delivered through a less‐risky process or design, or may be eliminated<br />

altogether. The PMOC shall clearly identify those risks that can be avoided or eliminated.<br />

Risk Reduction is a planned action that will either reduce the consequence or the likelihood of a<br />

risk event. The PMOC shall clearly identify the root cause of the risk event, how the root cause will<br />

be reduced by implementing the PMOC’s recommendation, and who the PMOC recommends within<br />

the Grantee organization or project team to carry out the risk mitigation scope element. The PMOC<br />

will also recommend progress‐reporting intervals for tracking the performance of mitigation<br />

measures as well as any integration with the Grantee’s overall program schedule and resource<br />

loading. All material assumptions shall be identified along with their rationales.<br />

Risk Acceptance results from the recognition, in the PMOC’s opinion, that further reduction of a<br />

particular risk would only come at the expense of unacceptable scope reduction or cost increase,<br />

etc. The PMOC shall clearly identify those risks that it recommends the Grantee accept as inherent<br />

to the project. Risk Acceptance often involves the consumption of project contingency funds,<br />

project schedule float, or an increase in either project budget or schedule.<br />

When providing recommendations, the PMOC shall only suggest Risk Acceptance when neither Risk<br />

Avoidance, Risk Reduction, nor Risk Transfer is available. However, PMOC recommendations shall<br />

recognize that there is a point in the implementation of the Grantee’s project (“break point”) where<br />

mitigation becomes increasingly difficult to effect and beyond which Risk Acceptance through the<br />

use of project contingency funds is the only effective means to treat project risk. This “break point”<br />

OP 40 Risk Assessment and Mitigation Review<br />

Revision 0, June 2008<br />

Page 10 of 16

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!