25.10.2013 Views

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

SCC40.02 thru 40.04 and SCC60:<br />

SCC70:<br />

SCC80:<br />

A BRF below 2.0 but above 1.75 implies the existence of Market Risk (bidding risk),<br />

indicated by uncertainty associated with reliable market data short of a project specific<br />

firm price;<br />

A BRF below 1.75 but above 1.35 indicates uncertainty associated with<br />

Geotechnical/Utility or similar activities exist. This is usually associated with<br />

activities occurring during the first 20% of construction. Full mitigation of risk during<br />

this period for simple LRT stations that are the equivalent of bus pads is indicated by a<br />

BRF of 1.35, while full mitigation of risk for certain elements such as guideway or<br />

systems is indicated by a BRF of 1.50.<br />

A BRF between 1.35 and 1.20 (or between 1.50 and 1.20 for certain elements such as<br />

guideway or systems) indicates uncertainty associated with mid-construction risks<br />

inclusive of major claims, delays, impacts, etc., usually associated with 75% complete,<br />

have been mitigated; β’s below this range imply increasing mitigation in the areas of<br />

normal change order activity.<br />

A BRF between 1.20 and 1.05 indicates uncertainty associated with late construction<br />

activities, including activities through start-up and substantial completion.<br />

A BRF of 1.0 implies that there is no risk or uncertainty of any kind associated with<br />

this item and represents the perfectly mitigated state of a project scope item.<br />

BRFs shall be estimated at 50-75% greater than that of SCCs 10 through 50 discussed<br />

above.<br />

BRFs shall be estimated at 75% greater than that of SCCs 10 through 50 discussed<br />

above.<br />

BRFs shall be estimated greater than that of SCCs 10 through 50 discussed above, and<br />

shall also be cross checked to accommodate the potential for project delay in the<br />

resultant 90th percentile estimate.<br />

Mean (or 50% Likely) Cost Element Value Establishment The mean and variance of the<br />

suggested range distribution are fully determined using the assumed lognormal distribution, the<br />

10th percentile estimate and the BRF. These calculations are modeled in the <strong>FTA</strong> Cost Risk<br />

Assessment Worksheet.<br />

Project Delivery Method For traditional project delivery methods, the PMOC shall use the above<br />

recommendations and procedures. Project Delivery methods affect the timing and scope of risk<br />

sharing but not the sequence of risk mitigation as discussed in OP‐35.<br />

Traditional project delivery methods (Design‐Bid‐Build) transfer or share risk at the completion of<br />

design and market risk mitigation. Alternative project delivery methods such as Design‐Build<br />

transfer or share some components of requirements, design, and market risk prior to the<br />

completion of all design and requirements risk, often sharing the market risk of subcontracting<br />

OP 40 Risk Assessment and Mitigation Review<br />

Revision 0, June 2008<br />

Page 6 of 16

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!