FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
SCC40.02 thru 40.04 and SCC60:<br />
SCC70:<br />
SCC80:<br />
A BRF below 2.0 but above 1.75 implies the existence of Market Risk (bidding risk),<br />
indicated by uncertainty associated with reliable market data short of a project specific<br />
firm price;<br />
A BRF below 1.75 but above 1.35 indicates uncertainty associated with<br />
Geotechnical/Utility or similar activities exist. This is usually associated with<br />
activities occurring during the first 20% of construction. Full mitigation of risk during<br />
this period for simple LRT stations that are the equivalent of bus pads is indicated by a<br />
BRF of 1.35, while full mitigation of risk for certain elements such as guideway or<br />
systems is indicated by a BRF of 1.50.<br />
A BRF between 1.35 and 1.20 (or between 1.50 and 1.20 for certain elements such as<br />
guideway or systems) indicates uncertainty associated with mid-construction risks<br />
inclusive of major claims, delays, impacts, etc., usually associated with 75% complete,<br />
have been mitigated; β’s below this range imply increasing mitigation in the areas of<br />
normal change order activity.<br />
A BRF between 1.20 and 1.05 indicates uncertainty associated with late construction<br />
activities, including activities through start-up and substantial completion.<br />
A BRF of 1.0 implies that there is no risk or uncertainty of any kind associated with<br />
this item and represents the perfectly mitigated state of a project scope item.<br />
BRFs shall be estimated at 50-75% greater than that of SCCs 10 through 50 discussed<br />
above.<br />
BRFs shall be estimated at 75% greater than that of SCCs 10 through 50 discussed<br />
above.<br />
BRFs shall be estimated greater than that of SCCs 10 through 50 discussed above, and<br />
shall also be cross checked to accommodate the potential for project delay in the<br />
resultant 90th percentile estimate.<br />
Mean (or 50% Likely) Cost Element Value Establishment The mean and variance of the<br />
suggested range distribution are fully determined using the assumed lognormal distribution, the<br />
10th percentile estimate and the BRF. These calculations are modeled in the <strong>FTA</strong> Cost Risk<br />
Assessment Worksheet.<br />
Project Delivery Method For traditional project delivery methods, the PMOC shall use the above<br />
recommendations and procedures. Project Delivery methods affect the timing and scope of risk<br />
sharing but not the sequence of risk mitigation as discussed in OP‐35.<br />
Traditional project delivery methods (Design‐Bid‐Build) transfer or share risk at the completion of<br />
design and market risk mitigation. Alternative project delivery methods such as Design‐Build<br />
transfer or share some components of requirements, design, and market risk prior to the<br />
completion of all design and requirements risk, often sharing the market risk of subcontracting<br />
OP 40 Risk Assessment and Mitigation Review<br />
Revision 0, June 2008<br />
Page 6 of 16