25.10.2013 Views

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Construction Risk is subdivided into: Early Construction Risk (composed of Geotechnical/Utility<br />

activities, usually associated with 20% complete), Mid‐Range Construction Risk (associated with<br />

coordination of contractors, etc.), and Start‐Up/ Substantial Completion Risk (associated with 90%<br />

complete).<br />

Although each of these categories of risk is associated with a particular project phase, if a risk event<br />

is not disposed of during a particular phase, it may survive as a risk exposure into a following<br />

phase.<br />

6.2.1.3 Risk Register<br />

The PMOC shall develop enumerated lists of identified Risk Events (Risk Register), which shall<br />

include a description of the potential risk event; its potential consequences and likelihood of<br />

occurrence; Risk Category; contract package; source document(s); and potential actions to mitigate<br />

the risk. The Risk Register is unlikely to be a collectively exhaustive representation of total project<br />

risk. Therefore, the Risk Register alone is insufficient to quantify risk, where a project‐level risk<br />

model is required.<br />

6.2.2 Cost Risk Assessment<br />

The Risk Assessment procedure consists of sequentially reducing, adjusting and conditioning<br />

Grantee and third party cost or schedule data in combination with prior, programmatic experience<br />

to empirically estimate parameters for the assumed risk distribution(s); and then utilizing these<br />

parameters as necessary to simulate the magnitude of risk and establish the potential responses to<br />

manage the risk. The PMOC shall obtain current documents, reports, and observations developed<br />

through prior analysis of the Grantee’s organization, and the project’s scope, cost estimate and<br />

schedule.<br />

6.2.2.1 Project Milestones<br />

Risk assessments shall be developed, at a minimum, for each of the following time‐based project<br />

milestones, where such milestones reflect future events:<br />

Entry in Preliminary Engineering;<br />

Entry into Final Design;<br />

FFGA award;<br />

40% of the contracted value has been bid and contracted;<br />

20% construction;<br />

50% construction;<br />

75% construction; and<br />

90% construction.<br />

Such milestones may be modified to reflect the specifics of the Grantee’s schedule, such as<br />

overlapping project phases. Where such milestones are more than one year apart, the PMOC shall<br />

develop supplemental milestones.<br />

6.2.2.2 Standard Cost Category (SCC) Risk Assessment<br />

Cost Risk Assessment Worksheet The <strong>FTA</strong> has developed a cost risk assessment worksheet<br />

template that contains the required formats and bases of calculations to properly execute the cost<br />

OP 40 Risk Assessment and Mitigation Review<br />

Revision 0, June 2008<br />

Page 3 of 16

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!