FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Construction Risk is subdivided into: Early Construction Risk (composed of Geotechnical/Utility<br />
activities, usually associated with 20% complete), Mid‐Range Construction Risk (associated with<br />
coordination of contractors, etc.), and Start‐Up/ Substantial Completion Risk (associated with 90%<br />
complete).<br />
Although each of these categories of risk is associated with a particular project phase, if a risk event<br />
is not disposed of during a particular phase, it may survive as a risk exposure into a following<br />
phase.<br />
6.2.1.3 Risk Register<br />
The PMOC shall develop enumerated lists of identified Risk Events (Risk Register), which shall<br />
include a description of the potential risk event; its potential consequences and likelihood of<br />
occurrence; Risk Category; contract package; source document(s); and potential actions to mitigate<br />
the risk. The Risk Register is unlikely to be a collectively exhaustive representation of total project<br />
risk. Therefore, the Risk Register alone is insufficient to quantify risk, where a project‐level risk<br />
model is required.<br />
6.2.2 Cost Risk Assessment<br />
The Risk Assessment procedure consists of sequentially reducing, adjusting and conditioning<br />
Grantee and third party cost or schedule data in combination with prior, programmatic experience<br />
to empirically estimate parameters for the assumed risk distribution(s); and then utilizing these<br />
parameters as necessary to simulate the magnitude of risk and establish the potential responses to<br />
manage the risk. The PMOC shall obtain current documents, reports, and observations developed<br />
through prior analysis of the Grantee’s organization, and the project’s scope, cost estimate and<br />
schedule.<br />
6.2.2.1 Project Milestones<br />
Risk assessments shall be developed, at a minimum, for each of the following time‐based project<br />
milestones, where such milestones reflect future events:<br />
Entry in Preliminary Engineering;<br />
Entry into Final Design;<br />
FFGA award;<br />
40% of the contracted value has been bid and contracted;<br />
20% construction;<br />
50% construction;<br />
75% construction; and<br />
90% construction.<br />
Such milestones may be modified to reflect the specifics of the Grantee’s schedule, such as<br />
overlapping project phases. Where such milestones are more than one year apart, the PMOC shall<br />
develop supplemental milestones.<br />
6.2.2.2 Standard Cost Category (SCC) Risk Assessment<br />
Cost Risk Assessment Worksheet The <strong>FTA</strong> has developed a cost risk assessment worksheet<br />
template that contains the required formats and bases of calculations to properly execute the cost<br />
OP 40 Risk Assessment and Mitigation Review<br />
Revision 0, June 2008<br />
Page 3 of 16