management labor and profit/fee. Such characterizations shall be adequately supported with analysis and<br />
rationales.<br />
The second subsection shall assess, evaluate and estimate the effective mitigation capacity of the subject<br />
contract package pricing/compensation components.<br />
Data shall be presented in a tabular format as applicable.<br />
Review and Analysis of Transferred Project Risk Mapping<br />
The section shall identify and characterize the project risk set that is identified as being allocated to the<br />
third party contract using Grantee or PMOC developed risk sets such as OP-40 models. Such<br />
characterizations shall be adequately supported with analysis and rationales. The objective is to present<br />
<strong>FTA</strong> with an estimate of the aggregate amount of eligible risk that is being transferred in terms of its<br />
expected value as well as what amount of residual risk is still being retained by the Grantee.<br />
Data shall be presented in a tabular format as applicable.<br />
Review and Analysis of Transfer Rate<br />
This first subsection shall present those transferred risks that the PMOC found occurred in the range of<br />
25-75%. The PMOC shall estimate the aggregate amount of Grantee risk for this class relative to the cost<br />
of the contracted mitigation capacity.<br />
The second subsection shall present those transferred risks that the PMOC found occurred in the range of<br />
less than 25%. The PMOC shall estimate the aggregate amount of Grantee risk for this class relative to the<br />
cost of the contracted mitigation capacity.<br />
The third subsection shall present those transferred risks that the PMOC found occurred in the range of<br />
more than 75% with special attention to those risks transferred at greater than 100%. The PMOC shall<br />
estimate the aggregate amount of Grantee risk for this class relative to the cost of the contracted<br />
mitigation capacity. Again, with special attention to those risks transferred above 100%.<br />
Data shall be presented in a tabular format as applicable.<br />
Review and Analysis of Value to Project<br />
This section shall identify and characterize the PMOC’s opinion as to the value of the project risk set that<br />
is identified as being allocated to third party contracts. Such characterizations shall be adequately<br />
supported with analysis and rationales. The objective is to present <strong>FTA</strong> with an estimate of the aggregate<br />
transfer rate and its effectiveness as well as what amount of residual risk is being retained by the Grantee.<br />
The PMOC shall also make recommendations as to the way in which this value can be increased or its<br />
associated cost can be decreased.<br />
Data shall be presented in a tabular format as applicable.<br />
Conclusion<br />
OP 35 Project Contingency and Contract Package Review<br />
Revision 0, June 2008<br />
Page 9 of 10