FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ... FTA Oversight Procedures - Federal Transit Administration - U.S. ...
degree of understanding among the parties involved, of uncertainties in quantifications of the risks. o Estimation of the expected value of the risk, including reasonable compensation for profit as compensation for risk acquisition (the “risk neutral point” or “neutral point”). It shall be assumed that competitive, market‐based pricing defines the risk neutral point as such compensation or pricing that neither contributes to nor detracts from the third party’s risk liability and indirectly, the Grantee’s overall project risk. The PMOC shall assume that 4% represents a profit or fee that is at the neutral point. o Estimation of the difference between the anticipated negotiated compensation for risk acquisition and the equivalent neutral point. Such difference shall be expressed as the ratio of the difference between the neutral point and the proposed compensation amount, divided by the neutral point. This ratio is herein called the transfer rate. Transfer rates above 75% represent an increasing potential for third‐party risk acceptance and a decreasing amount of Grantee risk sharing, as well as requiring less of an explicit description of allocated risk. Transfer rates over 75% are to be considered as increasingly effective but offering less value to the Grantee. Transfer rates below 75% of the risk’s expected value represent a potential increasing amount of risk to third parties and a potential of unexpected retained risk by the Grantee, perhaps indicating some ineffectiveness of the risk allocation. This potential for increased Grantee risk may arise from construction case law precedent and may be unrecognized or undisclosed by project participants. Transfer rates below 25% are to be considered ineffective. As appropriate, the PMOC shall make recommendations to achieve a more effective risk allocation strategy, to develop more effective negotiations for allocated risks, or to otherwise improve the value added by choice of project delivery method. 7.0 REPORT, PRESENTATION, RECONCILIATION 7.1 Cost and Schedule Contingency Reports Unless otherwise directed by the FTA, the delivered Spot Report will be sectioned as follows: Executive Summary Unless otherwise directed by the COTR/TOM, not to exceed 3 pages. Project Background Project descriptions and data shall be consistent with the Monitoring report guidance, current monitoring OP 35 Project Contingency and Contract Package Review Revision 0, June 2008 Page 7 of 10
eport and the most recent FTA New Start profile. Notwithstanding the foregoing, the task order manager or COTR may direct the PMOC to use an identifiable draft version of these materials. Review and Analysis of Project Contingency Conclusion Recommendations • Scope Review checklists for design and construction reviews. • Recommendations for Conditional Approval to Enter PE/FD • Recommendations for Project Development Agreement/FFGA. Appendix A: Grantee Project Data This section shall identify and characterize the Grantee’s structure and quality of the Grantee’s project data reviewed for the spot report or other deliverables. The intent is to determine the extent, nature, detail and quality of the Grantee project data and the steps the PMOC took to determine its value. The PMOC shall identify, and discuss Grantee or third party data it accepted without adjustment. Appendix B: Methodology The purpose of this section is to describe the PMOC’s methodology. Include other appendices as necessary or directed. 7.2 Contractual Risk Allocation Report Unless otherwise directed by the FTA, the delivered report will be sectioned as follows: Executive Summary Unless otherwise directed by the task order manager or COTR, not to exceed 3 pages. Project Background Project descriptions and data shall be consistent with the Monitoring report guidance, current monitoring report and the most recent FTA New Start profile. Notwithstanding the foregoing, FTA may direct the Contractor to use an identifiable draft version of these materials. Sub sectioning shall also include Guideway Components, Project Delivery Method, inclusive of the proposed Contract Packaging Strategy, and, as applicable, Master Planning for the Corridor. Review and Analysis of Contract Package Level Cost Mapping The first subsection shall identify and characterize the subject contract package pricing/compensation into cost accounting categories such as subcontracted direct costs, contractor direct labor, direct material, direct equipment, field and home office overheads, project contingency, engineering, construction OP 35 Project Contingency and Contract Package Review Revision 0, June 2008 Page 8 of 10
- Page 162 and 163: APPENDIX A Scope Review Checklist E
- Page 164 and 165: o Development of strategies for min
- Page 166 and 167: to then be backfilled or would othe
- Page 168 and 169: • Major or critical work details;
- Page 170 and 171: It is important to select a project
- Page 172 and 173: 6.2 Preliminary Document Review Upo
- Page 174 and 175: U.S. DOT Federal Transit Administra
- Page 176 and 177: o Level 4: Subdivide Level 3 as fol
- Page 178 and 179: • Is integrated with and makes ad
- Page 180 and 181: APPENDIX B Cost Estimate Review Che
- Page 182 and 183: o Confirm that cost estimates are b
- Page 184 and 185: 12) Appendices a) Grantee Project I
- Page 186 and 187: This sample of 118 cost items was s
- Page 188 and 189: consistently accurate. In addition,
- Page 190 and 191: SCC-10.02 Earth Excavation Although
- Page 192 and 193: The scope review identifies risk in
- Page 194 and 195: • Producer Price Index (PPI) - Th
- Page 196 and 197: APPENDICES PROJECT COST ESTIMATE ([
- Page 198 and 199: EXHIBIT D-1: PROJECT COST ESTIMATE
- Page 200 and 201: 3.0 OBJECTIVES FTA’s objective is
- Page 202 and 203: E) Lead times and durations for equ
- Page 204 and 205: activity durations. Critical path f
- Page 206 and 207: US DOT Federal Transit Administrati
- Page 208 and 209: orders may direct the PMOC to reeva
- Page 210 and 211: Design‐Build or CM‐GC), the pro
- Page 214 and 215: management labor and profit/fee. Su
- Page 216 and 217: US DOT Federal Transit Administrati
- Page 218 and 219: Construction Risk is subdivided int
- Page 220 and 221: Category or sub‐category cost ele
- Page 222 and 223: with the construction contractor. T
- Page 224 and 225: Management Plan; these recommendati
- Page 226 and 227: etween risk reduction and risk acce
- Page 228 and 229: 75% construction 85% 90% constructi
- Page 230 and 231: milestones, the value of expected m
- Page 232 and 233: U.S. DOT Federal Transit Administra
- Page 234 and 235: 4.2 Guidance coordination of platfo
- Page 236 and 237: communicate with the vehicle manufa
- Page 238 and 239: APPENDIX A FTA Request for Informat
- Page 240 and 241: APPENDIX B OP 41 ADA Review - Level
- Page 242 and 243: 4.1 Legislative • The Safe, Accou
- Page 244 and 245: 4) Cost estimate in year-of-expendi
- Page 246 and 247: U.S. DOT Federal Transit Administra
- Page 248 and 249: • Project Schedule (Master Schedu
- Page 250 and 251: d) Assessed safety and security iss
- Page 252 and 253: U.S. DOT Federal Transit Administra
- Page 254 and 255: • Interim Guidance on Design-Buil
- Page 256 and 257: (3) Appropriateness of the proposed
- Page 258 and 259: 7) Project Schedule The PMOC should
- Page 260 and 261: U.S. DOT Federal Transit Administra
degree of understanding among the parties involved, of uncertainties in<br />
quantifications of the risks.<br />
o Estimation of the expected value of the risk, including reasonable compensation for<br />
profit as compensation for risk acquisition (the “risk neutral point” or “neutral<br />
point”). It shall be assumed that competitive, market‐based pricing defines the risk<br />
neutral point as such compensation or pricing that neither contributes to nor detracts<br />
from the third party’s risk liability and indirectly, the Grantee’s overall project risk.<br />
The PMOC shall assume that 4% represents a profit or fee that is at the neutral point.<br />
o Estimation of the difference between the anticipated negotiated compensation for<br />
risk acquisition and the equivalent neutral point. Such difference shall be expressed<br />
as the ratio of the difference between the neutral point and the proposed<br />
compensation amount, divided by the neutral point. This ratio is herein called the<br />
transfer rate.<br />
Transfer rates above 75% represent an increasing potential for third‐party<br />
risk acceptance and a decreasing amount of Grantee risk sharing, as well as<br />
requiring less of an explicit description of allocated risk. Transfer rates over<br />
75% are to be considered as increasingly effective but offering less value to<br />
the Grantee.<br />
Transfer rates below 75% of the risk’s expected value represent a potential<br />
increasing amount of risk to third parties and a potential of unexpected<br />
retained risk by the Grantee, perhaps indicating some ineffectiveness of the<br />
risk allocation. This potential for increased Grantee risk may arise from<br />
construction case law precedent and may be unrecognized or undisclosed by<br />
project participants.<br />
Transfer rates below 25% are to be considered ineffective.<br />
As appropriate, the PMOC shall make recommendations to achieve a more effective risk<br />
allocation strategy, to develop more effective negotiations for allocated risks, or to otherwise<br />
improve the value added by choice of project delivery method.<br />
7.0 REPORT, PRESENTATION, RECONCILIATION<br />
7.1 Cost and Schedule Contingency Reports<br />
Unless otherwise directed by the <strong>FTA</strong>, the delivered Spot Report will be sectioned as follows:<br />
Executive Summary<br />
Unless otherwise directed by the COTR/TOM, not to exceed 3 pages.<br />
Project Background<br />
Project descriptions and data shall be consistent with the Monitoring report guidance, current monitoring<br />
OP 35 Project Contingency and Contract Package Review<br />
Revision 0, June 2008<br />
Page 7 of 10