FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ... FTA Oversight Procedures - Federal Transit Administration - U.S. ...

25.10.2013 Views

US DOT Federal Transit Administration TPM-20 Office of Engineering Project Management Oversight Oversight Procedure OP-35 Project Contingency and Contract Packaging Review _____________________________________________________________________________________ 1.0 PURPOSE To support FTA programmatic decisions as to the adequacy of Project Contingencies and third party contractual risk allocations and the soundness of Grantee management decisions regarding the development of risk allocations and usage of contingencies. To obtain the Project Management Oversight Contractor’s (PMOC) products that identify, characterize and analyze project contingency availability, status and forecasts for critical project scope milestones relative to that expected under forecasted conditions and sound engineering practices. The OP‐35 products support FTA’s programmatic goals for ensuring that Grantee management processes include a thorough understanding and implementation of risk informed, fundamentally sound project strategies. 2.0 BACKGROUND The role of theOP‐35 product is to identify, characterize and precisely describe critical elements of responses to project risk, including establishment of project cost and schedule contingencies, and contractual risk allocations. These products complement other risk information products, especially including those in OP‐40. These procedures are to be applied in consideration of project cost and schedule as well as other technical parameters such as service reliability. OP‐35 deliverables are intended to be fully sufficient to evaluate the adequacy, effectiveness, and efficiency of the Grantee’s management of contingency and contract packaging at any point during project implementation. 2.1.1 Cost and Schedule Contingency FTA has developed a significant amount of program experience to offer guidance to PMOCs and Grantees as to establishing various forms of contingency. In addition, studies such as TCRP’s 2005 report on “Managing Capital Costs of Major Federally Funded Public Transportation Projects” have evaluated cost and schedule variances on transit projects. These TCRP parameters were used to develop the requirements for the OP‐35 products. 2.1.2 Contractual Risk Allocation The Grantee’s choice of project delivery method and contracting strategy is integral to the Grantee’s Project Management Plan. This plan should demonstrate the Grantee’s technical approach and trade‐off analyses to obtaining the optimum allocation of risk that will achieve the preferred balance of project goals, including lowest overall project cost. FTA’s Project and Construction Management Guidelines note that risk should be considered in OP 35 Project Contingency and Contract Package Review Revision 0, June 2008 Page 1 of 10

selection of project delivery method, such that the likelihood of success is optimized. A companion operational procedure, OP‐40, additionally contains provisions designed to discover, analyze, and suggest approaches toward project delivery methods and contracting strategies that will ultimately assist in the delivering the most successful project. The fundamental principles involved in the OP‐35 contractual risk review is that risks should be allocated among the parties in proportion to their ability to manage the risks and absorb the consequences; that any transfer of risk to a third party is done so on an equitable basis of compensation given for risk accepted; and that risk remaining with the Grantee is fully recognized and an effective risk response plan has been developed. The Grantee’s project delivery methods and contracting plans, including its proposed terms and Conditions, should offer a holistic approach to ensuring that all forms of third party compensation, especially non‐competitive, negotiated compensation, is aligned with the principles above and actively supports successful implementation of the project. 3.0 OBJECTIVES FTA’s programmatic objective in the delivery of OP‐35 products is to obtain the PMOC’s recommendations as to the minimum contingency balances required to ensure completion of the Federally assisted project, as well as obtain characterizations and recommendations of contractually‐allocated risks. These products deliver inputs critical to the development of OP‐40 project strategy products that in turn support FTA’s achievement of its enterprise objectives. 4.0 REFERENCES The statutes, regulations, policies, guidance documents and circulars in OP 01 Administrative Conditions and Requirements apply. 5.0 PROJECT SPONSOR SUBMITTALS The PMOC shall obtain appropriate documentation to adequately investigate the project and complete the work described herein; such documentation may include the Project Cost Estimate, FFGA Baseline Cost Estimate (BCE) line items, project schedules, management plans, contracting plans, and other documentation as required. 6.0 SCOPE OF WORK Subject to the issuance of individual work orders, FTA may require the PMOC to perform the following subtasks as part of the products or services delivered under this guidance. Such work orders may reconfigure parts of the subtask deliverables, add sub deliverables, or otherwise accommodate development of project strategies inclusive of contingency management baselines, periodic reviews or “refreshments”, specialized quantitative capacity modeling or assessments, surveillance reporting and trends analyses. The requirement for contingency in the Grantee project may change as project implementation proceeds and information becomes available. Therefore, throughout the project lifetime, such work OP 35 Project Contingency and Contract Package Review Revision 0, June 2008 Page 2 of 10

selection of project delivery method, such that the likelihood of success is optimized. A companion<br />

operational procedure, OP‐40, additionally contains provisions designed to discover, analyze, and<br />

suggest approaches toward project delivery methods and contracting strategies that will ultimately<br />

assist in the delivering the most successful project.<br />

The fundamental principles involved in the OP‐35 contractual risk review is that risks should be<br />

allocated among the parties in proportion to their ability to manage the risks and absorb the<br />

consequences; that any transfer of risk to a third party is done so on an equitable basis of<br />

compensation given for risk accepted; and that risk remaining with the Grantee is fully recognized<br />

and an effective risk response plan has been developed.<br />

The Grantee’s project delivery methods and contracting plans, including its proposed terms and<br />

Conditions, should offer a holistic approach to ensuring that all forms of third party compensation,<br />

especially non‐competitive, negotiated compensation, is aligned with the principles above and<br />

actively supports successful implementation of the project.<br />

3.0 OBJECTIVES<br />

<strong>FTA</strong>’s programmatic objective in the delivery of OP‐35 products is to obtain the PMOC’s<br />

recommendations as to the minimum contingency balances required to ensure completion of the<br />

<strong>Federal</strong>ly assisted project, as well as obtain characterizations and recommendations of<br />

contractually‐allocated risks. These products deliver inputs critical to the development of OP‐40<br />

project strategy products that in turn support <strong>FTA</strong>’s achievement of its enterprise objectives.<br />

4.0 REFERENCES<br />

The statutes, regulations, policies, guidance documents and circulars in OP 01 Administrative<br />

Conditions and Requirements apply.<br />

5.0 PROJECT SPONSOR SUBMITTALS<br />

The PMOC shall obtain appropriate documentation to adequately investigate the project and<br />

complete the work described herein; such documentation may include the Project Cost Estimate,<br />

FFGA Baseline Cost Estimate (BCE) line items, project schedules, management plans, contracting<br />

plans, and other documentation as required.<br />

6.0 SCOPE OF WORK<br />

Subject to the issuance of individual work orders, <strong>FTA</strong> may require the PMOC to perform the<br />

following subtasks as part of the products or services delivered under this guidance.<br />

Such work orders may reconfigure parts of the subtask deliverables, add sub deliverables, or<br />

otherwise accommodate development of project strategies inclusive of contingency management<br />

baselines, periodic reviews or “refreshments”, specialized quantitative capacity modeling or<br />

assessments, surveillance reporting and trends analyses.<br />

The requirement for contingency in the Grantee project may change as project implementation<br />

proceeds and information becomes available. Therefore, throughout the project lifetime, such work<br />

OP 35 Project Contingency and Contract Package Review<br />

Revision 0, June 2008<br />

Page 2 of 10

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!