E) Lead times and durations for equipment and material manufacturing and delivery are adequate and complete, F) Logic for the physical construction constraints, such as transportation or access point restrictions, and temporary construction have been considered and are reasonable, G) Seasonal weather variations are accounted for, H) Labor and material availability have been factored into construction durations, I) Work efforts of similar nature that occur concurrently are identified and reasonably sequenced in the schedule to assure similar work activities can be accomplished with available labor and materials, J) Phasing due to planned right-of-way acquisition provides sufficient work area(s) for efficient use of resources, K) Adequately and completely reflects sponsor procurements, schedule and cost forecasts, and construction change orders, L) The Contractor shall assess and evaluate the proposed schedule duration to at least three other similar projects from the FTA database and analyze the variances down the SCC level. 6.1.3 External Activities and Constraints A) Schedule contains a full range of activities including FTA related approvals (DEIS, FEIS, LONP, FFGA); procurement and performance of civil/facilities and systems final design; right-of-way acquisition; wetland mitigation; utility/agency agreements; utility relocation; civil and systems contract procurement; civil and systems construction; agency operations and maintenance mobilization; and integrated pre-revenue testing, B) Activity durations include adequate time for project reviews by applicable local, state and federal jurisdictions and affected third parties, C) FTA review periods, including milestones and activities leading to the FFGA such as development of Risk Management Plans, Safety and Security Management Plans, Project Development and Execution Plans, etc. D) Funding milestones from non-FTA sources 6.1.4 Risk Identification A) Embedded schedule contingencies are identified and assessed as adequate relative to project duration, B) Identify and separately list risks discovered in the schedule review and evaluate the potential impact of these risks on the schedule, scope, and cost, C) Estimate a probability of schedule slippage for critical path activities. 7.0 REPORT, PRESENTATION, RECONCILIATION Prepare a written report in the format discussed below. Attach the sponsor’s most current SCC schedule. Embed references to, or exhibits from, sponsor’s schedule to explain your analysis, findings, and recommendations. OP 34 Project Schedule Review Revision 0, June 2008 Page 4 of 7
Present the findings, conclusions and recommendations to FTA headquarters and regional staff and the Project Sponsor either in a teleconference or in person. In an extended working session, reconcile findings and conclusions with the Project Sponsor so that disagreements if any are reconciled to the extent possible. Integrate and summarize available information and data for the project, providing professional opinion, analysis, information, data and descriptive text in an accessible and understandable format. Opinions shall be supported by data tables similar in nature to those depicted in 8.1. 7.1 Reporting Format Reference the general requirements contained in OP‐01. 7.2 Spot Report Contents and Format Unless otherwise directed by the WOM or COTR, the delivered Spot Report will be sectioned as follows: 7.2.1 Primary Deliverable I) Executive Summary • Unless otherwise directed by the COTR/TOM, not to exceed 3 pages. II) Project Background • Project descriptions and data shall be consistent with the Monitoring report guidance, current monitoring report and the most recent FTA New Start profile. Notwithstanding the foregoing, the TOM or COTR may direct the Contractor to use an identifiable draft version of these materials. III) Methodology • Describe the methodology used to develop information and documentation used in subsequent analyses, • Present, discuss, and thoroughly demonstrate the Contractor’s approach to identifying schedule contingency. IV) Review and Analysis of Project Schedule • Assessment and evaluation shall be in 7 subsections: Critical Areas of Concern and Risks, Schedule, Technical Reviews, Resource loading, Project Calendars, Interfaces and Project Critical Path, • Data tables and histograms are to be provided within individual sections; see 8.1 for samples, • Present the review and evaluation of schedule elements in the Grantee’s project schedule that are functionally equivalent to schedule contingency but not identified as such, including forced float or dummy activities, • Present and discuss an analysis of the sponsor’s proposed critical path for the project schedule including an assessment of its validity and the reasonableness of OP 34 Project Schedule Review Revision 0, June 2008 Page 5 of 7
- Page 152 and 153: 2.2 The New Starts Process New Star
- Page 154 and 155: 3.0 OBJECTIVES During the initial e
- Page 156 and 157: 7.0 REPORT, PRESENTATION, RECONCILI
- Page 158 and 159: provisions) to make detailed design
- Page 160 and 161: 6) Identify any unknown or uncertai
- Page 162 and 163: APPENDIX A Scope Review Checklist E
- Page 164 and 165: o Development of strategies for min
- Page 166 and 167: to then be backfilled or would othe
- Page 168 and 169: • Major or critical work details;
- Page 170 and 171: It is important to select a project
- Page 172 and 173: 6.2 Preliminary Document Review Upo
- Page 174 and 175: U.S. DOT Federal Transit Administra
- Page 176 and 177: o Level 4: Subdivide Level 3 as fol
- Page 178 and 179: • Is integrated with and makes ad
- Page 180 and 181: APPENDIX B Cost Estimate Review Che
- Page 182 and 183: o Confirm that cost estimates are b
- Page 184 and 185: 12) Appendices a) Grantee Project I
- Page 186 and 187: This sample of 118 cost items was s
- Page 188 and 189: consistently accurate. In addition,
- Page 190 and 191: SCC-10.02 Earth Excavation Although
- Page 192 and 193: The scope review identifies risk in
- Page 194 and 195: • Producer Price Index (PPI) - Th
- Page 196 and 197: APPENDICES PROJECT COST ESTIMATE ([
- Page 198 and 199: EXHIBIT D-1: PROJECT COST ESTIMATE
- Page 200 and 201: 3.0 OBJECTIVES FTA’s objective is
- Page 204 and 205: activity durations. Critical path f
- Page 206 and 207: US DOT Federal Transit Administrati
- Page 208 and 209: orders may direct the PMOC to reeva
- Page 210 and 211: Design‐Build or CM‐GC), the pro
- Page 212 and 213: degree of understanding among the p
- Page 214 and 215: management labor and profit/fee. Su
- Page 216 and 217: US DOT Federal Transit Administrati
- Page 218 and 219: Construction Risk is subdivided int
- Page 220 and 221: Category or sub‐category cost ele
- Page 222 and 223: with the construction contractor. T
- Page 224 and 225: Management Plan; these recommendati
- Page 226 and 227: etween risk reduction and risk acce
- Page 228 and 229: 75% construction 85% 90% constructi
- Page 230 and 231: milestones, the value of expected m
- Page 232 and 233: U.S. DOT Federal Transit Administra
- Page 234 and 235: 4.2 Guidance coordination of platfo
- Page 236 and 237: communicate with the vehicle manufa
- Page 238 and 239: APPENDIX A FTA Request for Informat
- Page 240 and 241: APPENDIX B OP 41 ADA Review - Level
- Page 242 and 243: 4.1 Legislative • The Safe, Accou
- Page 244 and 245: 4) Cost estimate in year-of-expendi
- Page 246 and 247: U.S. DOT Federal Transit Administra
- Page 248 and 249: • Project Schedule (Master Schedu
- Page 250 and 251: d) Assessed safety and security iss
E) Lead times and durations for equipment and material manufacturing and delivery are<br />
adequate and complete,<br />
F) Logic for the physical construction constraints, such as transportation or access point<br />
restrictions, and temporary construction have been considered and are reasonable,<br />
G) Seasonal weather variations are accounted for,<br />
H) Labor and material availability have been factored into construction durations,<br />
I) Work efforts of similar nature that occur concurrently are identified and reasonably<br />
sequenced in the schedule to assure similar work activities can be accomplished with<br />
available labor and materials,<br />
J) Phasing due to planned right-of-way acquisition provides sufficient work area(s) for<br />
efficient use of resources,<br />
K) Adequately and completely reflects sponsor procurements, schedule and cost forecasts, and<br />
construction change orders,<br />
L) The Contractor shall assess and evaluate the proposed schedule duration to at least three<br />
other similar projects from the <strong>FTA</strong> database and analyze the variances down the SCC<br />
level.<br />
6.1.3 External Activities and Constraints<br />
A) Schedule contains a full range of activities including <strong>FTA</strong> related approvals (DEIS, FEIS,<br />
LONP, FFGA); procurement and performance of civil/facilities and systems final design;<br />
right-of-way acquisition; wetland mitigation; utility/agency agreements; utility relocation;<br />
civil and systems contract procurement; civil and systems construction; agency operations<br />
and maintenance mobilization; and integrated pre-revenue testing,<br />
B) Activity durations include adequate time for project reviews by applicable local, state and<br />
federal jurisdictions and affected third parties,<br />
C) <strong>FTA</strong> review periods, including milestones and activities leading to the FFGA such as<br />
development of Risk Management Plans, Safety and Security Management Plans, Project<br />
Development and Execution Plans, etc.<br />
D) Funding milestones from non-<strong>FTA</strong> sources<br />
6.1.4 Risk Identification<br />
A) Embedded schedule contingencies are identified and assessed as adequate relative to<br />
project duration,<br />
B) Identify and separately list risks discovered in the schedule review and evaluate the<br />
potential impact of these risks on the schedule, scope, and cost,<br />
C) Estimate a probability of schedule slippage for critical path activities.<br />
7.0 REPORT, PRESENTATION, RECONCILIATION<br />
Prepare a written report in the format discussed below. Attach the sponsor’s most current SCC<br />
schedule. Embed references to, or exhibits from, sponsor’s schedule to explain your analysis,<br />
findings, and recommendations.<br />
OP 34 Project Schedule Review<br />
Revision 0, June 2008<br />
Page 4 of 7