3.0 OBJECTIVES<br />

<strong>FTA</strong>’s objective is to determine whether the sponsor’s project schedule is sufficiently developed<br />

to establish the validity of the longest path of the project (leading to the Revenue Operations<br />

Date), that critical areas such as right‐of‐way acquisition, utility relocation, wetland mitigation<br />

and construction are sufficient in detail to confirm if the schedule is reasonable, and to estimate<br />

a probability of schedule slippage.<br />

The reviewer is to validate the usefulness of the schedule as a project management tool, identify<br />

problems, provide technical assistance, and actively solve schedule problems with the project<br />

sponsor. In a report to <strong>FTA</strong> and the project sponsor, the reviewer is to document its findings,<br />

professional opinions and recommendations and reconcile these with the sponsor.<br />

In addition, identification of individual project schedule elements that indicate poor definition,<br />

uncertain constraints, or insufficient sequencing will reveal risk to the project. This provides <strong>FTA</strong><br />

with an effective approach to accomplish risk management in that the reviewer evaluates the<br />

inadequately defined areas and makes recommendations as to their disposition. This ensures<br />

<strong>FTA</strong>’s risk products satisfy the oversight requirement for accuracy and completeness.<br />

Deliverables should be commensurate with the overall progress of the program, taking into<br />

consideration actual progress and expenditure data. Variances from the Project Management<br />

Plan and the planned Full Funding Grant Agreement (FFGA) should be thoroughly discussed.<br />

4.0 REFERENCES<br />

4.1 Regulatory<br />

[NOTE: FURTHER REFERENCES AND LIVE LINKS TO BE ADDED]<br />

The statutes, regulations, policies, guidance documents and circulars in the Appendix in OP 01<br />

Administrative Conditions and Requirements apply. Particular attention should be given to OPs<br />

32, 33, 35, and 40.<br />

4.2 Appendices<br />

The following Appendices are included this guidance:<br />

8.1 ‐ Sample Section with Data Table<br />

8.2 ‐ Typical Construction Sequencing<br />

5.0 PROJECT SPONSOR SUBMITTALS<br />

In advance of performing the review, meet with the project sponsor and its staff and consultants,<br />

discuss the purpose of the review, and obtain information as required, including but not limited<br />

to, the sponsor’s schedule development and control process, the latest schedules produced and<br />

supporting scope and cost information. Information should be received in either electronic or<br />

hard copy form, appropriate to the type of information developed, and archived in accordance<br />

with current <strong>FTA</strong> procedures.<br />

OP 34 Project Schedule Review<br />

Revision 0, June 2008<br />