25.10.2013 Views

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

This escalation amount was computed as follows. The escalation costs of $56,691,000 in the Preliminary<br />

Design Project Cost Estimate Summary represents 14.4% of the Project Subtotal plus Project Level<br />

Contingency ($393,434,258). Furthermore, a 1.04 factor (4% escalation) compounded for 3.5 years<br />

yields approximately 1.147 (or 14.7%). Therefore, a 1.0505 factor (5.05%) compounded for 3.5 years is<br />

equivalent to 1.1882 (or 18.82%). By applying this 18.82% to $393,434,258, an escalation cost of<br />

$74,045,000 is computed.<br />

As noted previously, the implementation schedule has a measurable impact upon the eventual capital cost<br />

of the completed projects. Any delays or slippage to the schedule in the performance of the design and<br />

construction activities will result in higher costs than estimated. As such, if these schedules are extended,<br />

the costs will likely increase from these estimates.<br />

The most common delays are those that are outside of the [Grantee’s] control, such as weather, utility<br />

relocation and right-of-way acquisition. The current schedule for this project lacks sufficient detail in<br />

these areas to estimate the probability of any delay with reasonable accuracy.<br />

However, by reference to the “Managing Capital Costs of Major <strong>Federal</strong>ly Funded Public Transportation<br />

Projects - Final Report,” June 2006, <strong>Transit</strong> Cooperative Transportation Research Program, the average<br />

delays for federally funded public transit projects were 1.0 year for design and 0.8 year for construction.<br />

Thus, an average delay of 1.8 years was used for this project to estimate any additional escalation impacts.<br />

By considering only a design and construction schedule delay and/or extension of 1.8 years, the project’s<br />

escalation cost would increase by $34,213,000 to $90,904,000. This escalation amount was computed as<br />

follows. The escalation costs of $56,691,000 in the [Grantee’s] Cost Estimate Summary represents 14.4%<br />

of the Project Subtotal plus Project Level Contingency ($393,434,258). Furthermore, a 1.04 factor (4%<br />

escalation) compounded for 3.5 years yields approximately 1.147 (or 14.7%). Therefore, a 1.04 factor<br />

(4.00%) compounded for 5.3 years (3.5 yr + 1.8 yr) is equivalent to 1.2311 (or 23.11%). By applying this<br />

23.11% to $393,434,258, an escalation cost of $90,904,000 is computed, which yields a $34,213,000<br />

variance with the estimated escalation cost of $56,691,000 used in the [Grantee’s] Project Cost Estimate<br />

Summary.<br />

A worst case scenario for the escalation cost impact could be calculated with an escalation percentage of<br />

5.05% and an extension or delay of the design and construction schedule by 1.8 years. Accordingly, the<br />

escalation impact would be $60,699,000. This escalation variance was calculated as follows. A 1.0505<br />

factor (5.05% escalation) compounded for 5.3 years (3.5 yr + 1.8 yr) yields approximately 1.2984 (or<br />

29.84%). Applying this 29.84% to $393,434,258 (Project Subtotal plus Project Level Contingency)<br />

results in an escalation cost of $117,390,000, or a $60,699,000 variance with the estimated escalation cost<br />

of $56,691,000 used in the Preliminary Design Project Cost Estimate Summary.<br />

In summary, the escalation costs variance has the potential to range between $17,350,000 and<br />

$60,699,000.<br />

OP 33 Capital Cost Estimate Review<br />

Revision 0, June 2008<br />

Page D-11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!