FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
The unit costs were also checked with [commercial cost index] Heavy Construction Cost Data. The unit<br />
costs in this reference source were adjusted to reflect [local area] pricing by using the respective city<br />
indices. These indices represent relative construction factors (or multipliers) for material and installation<br />
costs, as well as the weighted average for total-in-place costs for each CSI Master Format division. The<br />
[commercial cost index] Weighted Average Total (Material plus Labor) City Cost Indices for [local<br />
reference] were used to adjust [commercial cost index] unit costs to these [local reference] cities.<br />
It should be noted that in the PMOC cost review, the sponsor unit costs were initially assumed to be<br />
unburdened, and as such compared favorably with [commercial cost index] values and industry norms. In<br />
confirming such inferences with the sponsor unit costs are known to be unburdened with General<br />
Conditions cost, they are low when compared with the previously mentioned sources and pose significant<br />
cost risk.<br />
[Grantee] does not allow a separate line item for General Conditions and typically incorporates the costs<br />
for General Conditions in their project estimate unit costs, with some items addressed as specific line<br />
items or cost percentage add-ons. [Grantee] addresses Mobilization, which can be included in General<br />
Conditions, as a separate line item.<br />
Specific cost items reviewed are identified in Appendix [XX].<br />
Cost estimate quantities used in the design were developed with [software name], and were based on the<br />
application of guidance from the above mentioned references as well as other sources such as sponsor’s<br />
Surveys and Mapping, supplemental field surveys conducted by [consultant name], and inspection reports<br />
provided by [consultant name] for [named bridges]. Quantities were also based on coordination and<br />
advice from sponsor, and on engineering judgment.<br />
Cost estimate totals for minor items and Lump Sum/Miscellaneous Items were generated mainly by either<br />
cost CER or lump sum. Quantities for these items were also based on coordination and advice from<br />
sponsor, and on engineering judgment.<br />
Potential Cost Impacts<br />
General Conditions<br />
General Conditions are generally defined to include such items as traffic control and rerouting,<br />
specialized equipment, temporary utility connections and service. Grantee does not allow a separate line<br />
item for General Conditions and typically incorporates the costs for General Conditions in their project<br />
estimate unit costs, with some items addressed as specific line items or cost percentage add-ons. Grantee<br />
addresses Mobilization, which can be included in General Conditions, as a separate item.<br />
As discussed above, the unit costs are now known to be burdened with General Conditions cost, as such<br />
they are low when compared with the previously mentioned sources and pose significant cost risk. It is<br />
recommended that General Conditions be applied at a rate of 20% for guideway and track items (SCC-10)<br />
and at a rate of 10% for sitework items (SCC 40). Cost estimates for stations (SCC-20), support facilities<br />
(SCC-30), and systems (SCC-50) should be considered to include the cost of General Conditions within<br />
the cost allowances included. Mobilization should also be backed-out of the SCC-40 category, as it<br />
currently is rolled up in the cost estimate, and be applied at a rate of 7.5% to all affected line items<br />
throughout the SCC categories.<br />
OP 33 Capital Cost Estimate Review<br />
Revision 0, June 2008<br />
Page D-5