FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ... FTA Oversight Procedures - Federal Transit Administration - U.S. ...

25.10.2013 Views

This sample of 118 cost items was selected randomly from each of the corresponding cost item strata defined above. Lump sum, unit cost and cost estimating relationship cost items were segmented by amount into the larger and smaller values. Sampling rates selected for each cost item segment were based on a higher sample rate for the higher cost items and a lower rate for the lower cost items. The overall sampling rate objective was established at 15%. The specific sampling rates for each cost item category were selected to fulfill the overall objective and emphasize the higher cost items with the higher sampling rates. Random selection was completed through assignment of unique cost item numbers and a random number generator selection from each of these strata. The combined sample size of 17% exceeds the cost item objective of 15%. The specific cost items selected were provided to the cost evaluation team for the detailed analysis. The PMOC team reviewed the various cost documents provided by the sponsor. The following outline describes the steps applied to review the Project Cost Estimate: 1) Characterization or Stratification of Cost Items a) Characterize estimate data into one of three cost item categories or classifications -- Lump Sum, Unit Cost or Cost Estimate Relationship. b) Select sample totals based on individual sampling rates for each category. c) Identify cost items for detailed review based on random selection of individual cost items. 2) Mechanical Check of Estimate a) Mathematically sum all lump-sum prices, unit price and quantity calculations, and cost estimating relationships to confirm the sponsor’s total cost estimate. b) Perform a mathematical check of all sampled unit price or quantity calculations. c) Mathematically check the cross-walk and cost sums from the contract packages to the FTA Standard Cost Categories. 3) Comparison to Industry Standards a) Review sampled unit prices and quantities for conformance to industry standards, regional variations or other unique characteristics. b) Check sampled unit costs of similar items used in differing conditions to ensure local conditions and difficulty factors were considered in the individual estimated units. c) Check sampled quantities to confirm basis of calculations from design documents. 4) Correspondence with Scope Review a) Cross check sampled quantity estimates with the project scope contained in the design documents to determine degree of correlation between the design deliverables and the project cost estimate down to the 2nd level WBS. b) Perform general “Overview” of total estimate to give it a “sanity check” and ensure that all major components appear. c) Review sample quantities for reasonableness and to be representative of industry standards and the design scope of work with respect to major components. 5) Evaluate Contract Package Elements a) Assess certain contract package elements as to requirements and associated reviewer payments, characterizing elements as: i) Contract requirements for specific services such as QA/QC and scheduling that would be material elements in the development of bids; ii) Elements of contract language that would reasonably serve as a basis for additional compensation not part of a scheduled payment item; iii) Restrictive schedule or mobilization requirements that would be material pricing elements in developing a bid; iv) Geotechnical data and pricing approach to changed conditions; OP 33 Capital Cost Estimate Review Revision 0, June 2008 Page D-2

v) Unit pricing and allowed variability in unit pricing. 6) Supporting documentation and assumptions for sponsor’s general conditions cost estimate. a) Develop an independent, detailed general conditions cost estimate of the three largest construction contracts and of the systems work. 7) Escalation and Inflation Review a) Building up from the second SCC level, evaluate uniformity of application of escalation and inflation factors. b) Compare escalation and inflation factors used by sponsor to Producer Price Index data from the Bureau of Labor and Statistics (http://www.bls.gov) and other sources such as ENR, Means, Richardson, etc. to ensure adequate escalation and inflation cost is included to carry the project to the mid-point of construction (the assumed time when contract unit awards will be complete). REVIEW AND ANALYSIS OF PROJECT COST The PMOC team reviewed the cost estimate documentation supplied by sponsor, including packages for line contracts, stations contracts and breakout contracts (the list of documents reviewed is provided in Appendix). Sponsor provided the cost estimate for each contract package in electronic format and the estimate backup documentation in hard-copy format. The cost estimate and backup documentation reviewed was dated [date] . A summary of the [title of Grantee cost estimate] is provided as Appendix [XX]. The backup documentation was well organized and presented in a clear and concise manner. Having both the electronic files and hard-copy documentation facilitated the cost item review and analysis, as well as permitted the tracking of costs and quantities from the individual line items to project or contract cost estimate to ensure proper traceability and application. A randomly selected group of project quantities, unit costs, CERs, and lump sums was reviewed and validated, and the mechanical checks were deemed to be reliable and mathematically correct. Consequently, the level of document and estimate detail is commensurate for a project at this stage of design. Cost Item Classification The approach for planning the cost item analysis for this risk assessment was to identify and categorize each cost item in the sponsor’s estimate. The cost items of the estimate were analyzed and categorized by: 1) Unit Cost or Quantity supported or not supported on the design deliverables, 2) Cost Estimating Relationships (CER), and 3) Lump Sum. The cost items were further categorized by large and small, determined by a break point of $1 million. Cost items are large if their value is greater or equal to $1 million, while items lower than this are considered small cost items. A summary of the Grantee’s cost estimate, including PMOC’s recommendations, classified into unit cost, CER and lump sum is provided in Appendix [XX]. This estimate classification also categorizes the budget by: a) Drawings/Specifications, b) Schedule (includes escalation), c) Design Report, and d) General Conditions. Costs are classified into these categories on the basis of their estimate (how it was derived) and the extent of project definition. Mechanical Check Quality and mathematical checks for accuracy and traceability were performed at both a micro and macro level on the Project Cost Estimate. Individual line items for the Line, Stations, and Breakout Contracts were checked and summed to confirm the title level subtotals. This was performed manually with a calculator and electronically by reviewing the spreadsheet formulas. These computed subtotals were OP 33 Capital Cost Estimate Review Revision 0, June 2008 Page D-3

This sample of 118 cost items was selected randomly from each of the corresponding cost item strata<br />

defined above. Lump sum, unit cost and cost estimating relationship cost items were segmented by<br />

amount into the larger and smaller values. Sampling rates selected for each cost item segment were based<br />

on a higher sample rate for the higher cost items and a lower rate for the lower cost items. The overall<br />

sampling rate objective was established at 15%. The specific sampling rates for each cost item category<br />

were selected to fulfill the overall objective and emphasize the higher cost items with the higher sampling<br />

rates. Random selection was completed through assignment of unique cost item numbers and a random<br />

number generator selection from each of these strata. The combined sample size of 17% exceeds the cost<br />

item objective of 15%. The specific cost items selected were provided to the cost evaluation team for the<br />

detailed analysis.<br />

The PMOC team reviewed the various cost documents provided by the sponsor. The following outline<br />

describes the steps applied to review the Project Cost Estimate:<br />

1) Characterization or Stratification of Cost Items<br />

a) Characterize estimate data into one of three cost item categories or classifications -- Lump<br />

Sum, Unit Cost or Cost Estimate Relationship.<br />

b) Select sample totals based on individual sampling rates for each category.<br />

c) Identify cost items for detailed review based on random selection of individual cost items.<br />

2) Mechanical Check of Estimate<br />

a) Mathematically sum all lump-sum prices, unit price and quantity calculations, and cost<br />

estimating relationships to confirm the sponsor’s total cost estimate.<br />

b) Perform a mathematical check of all sampled unit price or quantity calculations.<br />

c) Mathematically check the cross-walk and cost sums from the contract packages to the <strong>FTA</strong><br />

Standard Cost Categories.<br />

3) Comparison to Industry Standards<br />

a) Review sampled unit prices and quantities for conformance to industry standards, regional<br />

variations or other unique characteristics.<br />

b) Check sampled unit costs of similar items used in differing conditions to ensure local<br />

conditions and difficulty factors were considered in the individual estimated units.<br />

c) Check sampled quantities to confirm basis of calculations from design documents.<br />

4) Correspondence with Scope Review<br />

a) Cross check sampled quantity estimates with the project scope contained in the design<br />

documents to determine degree of correlation between the design deliverables and the project<br />

cost estimate down to the 2nd level WBS.<br />

b) Perform general “Overview” of total estimate to give it a “sanity check” and ensure that all<br />

major components appear.<br />

c) Review sample quantities for reasonableness and to be representative of industry standards and<br />

the design scope of work with respect to major components.<br />

5) Evaluate Contract Package Elements<br />

a) Assess certain contract package elements as to requirements and associated reviewer<br />

payments, characterizing elements as:<br />

i) Contract requirements for specific services such as QA/QC and scheduling that would be<br />

material elements in the development of bids;<br />

ii) Elements of contract language that would reasonably serve as a basis for additional<br />

compensation not part of a scheduled payment item;<br />

iii) Restrictive schedule or mobilization requirements that would be material pricing elements<br />

in developing a bid;<br />

iv) Geotechnical data and pricing approach to changed conditions;<br />

OP 33 Capital Cost Estimate Review<br />

Revision 0, June 2008<br />

Page D-2