FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
FTA Oversight Procedures - Federal Transit Administration - U.S. ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
U.S. DOT <strong>Federal</strong> <strong>Transit</strong> <strong>Administration</strong><br />
TPM-20 Office of Engineering<br />
Project Management <strong>Oversight</strong><br />
<strong>Oversight</strong> Procedure 32E - Project Delivery Method Review<br />
______________________________________________________________________________<br />
1.0 PURPOSE<br />
The purpose of this <strong>Oversight</strong> Procedure is to describe the review, analysis and recommendation<br />
procedures and reporting requirements expected by <strong>Federal</strong> <strong>Transit</strong> <strong>Administration</strong> (<strong>FTA</strong>) from the<br />
Project Management <strong>Oversight</strong> Contractor (PMOC) with regard to the Grantee’s plan for project<br />
delivery.<br />
This review is meant to determine whether the delivery method or methods selected are appropriate to<br />
the project or corresponding project element and whether the Grantee has the technical capacity and<br />
capability to successfully implement the selected methods. For these purposes, Project Delivery<br />
Method is defined as the overall approach selected by the Grantee to contract for those services<br />
necessary to place the project in revenue service. The proposed definition would include engineering<br />
services, construction services, procurement of vehicles, procurement of “owner furnished materials”<br />
such as rail materials or other long lead-time items, and potentially the operation and maintenance of<br />
the completed system. The definition would also include the segmentation of the project into logical<br />
segments or contract packages and the procurement method selected for each package.<br />
2.0 BACKGROUND<br />
The typical New Start project is the sum of several discrete elements, including but not limited to<br />
professional services such as engineering and construction management, equipment such as rail transit<br />
or bus rapid transit vehicles and non-revenue vehicles; materials such as rail and ties, the construction<br />
of various things ranging from the rail way or road way to stations to maintenance facilities, the<br />
acquisition of rights-of-way, the administration and management by the grantee’s staff, and insurance.<br />
The largest proportion of the project’s budget is associated with the design, and construction or<br />
acquisition of the capital elements of the project, including those services necessary to design the<br />
facilities. The focus of this review is on the Grantee’s plan for acquiring the capital elements of the<br />
project.<br />
A variety of project delivery methods or contracting techniques are available to Grantees. The most<br />
common method involves the use of a design consultant to prepare drawings and specifications which<br />
are attached to contract documents and then used to solicit competitive bids for construction. This is<br />
often referred to as design-bid-build. Other alternative contracting methods include design-build,<br />
design-build-operate and maintain, and the construction manager at-risk or construction<br />
manager/general contractor (CM/GC) approach. All of these delivery methods are viable and have<br />
been used successfully, however, some work better than others in particular situations. For example, a<br />
transit station parking garage might be a good candidate for design-build because the owner’s primary<br />
concern is functionality, whereas a church would not be a good design-build candidate because of the<br />
parishioners’ need for control of the ornate architectural design.<br />
OP 32E Project Delivery Method Review<br />
Revision 0, June 2008<br />
Page 1 of 5