• Project drawings, project narratives, design criteria, specifications<br />
• Information on third parties, description of interface, status of negotiations/agreements<br />
• Project Management Plan<br />
6.0 SCOPE OF WORK<br />
The PMOC shall assess the completeness of NEPA documentation and the level to which<br />
environmental impacts and mitigations are reflected in the project drawings and specifications so as to<br />
provide a sound basis for the project cost estimate and schedule. The PMOC shall assess the project<br />
documentation and follow these procedures:<br />
• Review and analyze the pertinent information available for completeness, adequacy,<br />
consistency, and appropriateness of the level of detail given the phase of the work;<br />
• Identify any and all discrepancies;<br />
• State findings in descending order of importance (most likely -- largest consequences, least<br />
likely -- moderate/minor consequences) and make recommendations for modifications or<br />
additional work by the project sponsor along with a time frame for the performance of the<br />
work;<br />
• Make recommendations and provide professional opinions.<br />
Review for content as follows:<br />
• Confirm consistency between the environmental document and the project drawings,<br />
narratives, specifications, in how the Project Scope is defined and portrayed; verify that<br />
impacts and mitigations are fully reflected in the project drawings, narratives, specifications,<br />
cost estimate and schedule.<br />
• Review the project sponsor's operating budget to confirm that it reflects the agency’s existing<br />
operation and future operation when the project is built;<br />
• Review the project sponsor's capital cost estimate to confirm that it reflects the defined scope<br />
and schedule;<br />
• Prior to entry to PE:<br />
o Confirm that the Project sponsor has considered a sufficient array of alternatives and<br />
has taken the necessary steps in AA to effectively document the selection of the locally<br />
preferred alternative and other conclusions reached.<br />
o Notify <strong>FTA</strong> immediately if it appears that a reasonable alternative was omitted from the<br />
alternatives analysis.<br />
o Confirm that the LPA was adopted into the MPO's LRTP by obtaining a copy of the<br />
plan. Verify that the Project sponsor’s project scope is included and documented.<br />
o Verify that the LRTP is financially constrained.<br />
OP 32B Environmental Document (NEPA) Review for New Starts Projects<br />
Revision 0, June 2008<br />