3.0 OBJECTIVES<br />

During the initial environmental phase, a measure of engineering and conceptual design must be<br />

performed to support the AA and assessment of environmental impacts. After the selection of the LPA<br />

on which the draft environmental documentation is based, more advanced design work is needed to<br />

define the project and to establish the preliminary project scope, budget, and schedule. The project<br />

sponsor’s request for approval of the project to enter PE is based on this information. From this point<br />

on, <strong>FTA</strong> may direct the PMOC to perform this review.<br />

The PMOC shall assess and evaluate the project sponsor’s environmental documents, project drawings,<br />

project narratives, design criteria, specifications, and material third party project information.<br />

Additionally, the PMOC shall characterize the level to which the project sponsor has reflected<br />

potential environmental impacts and mitigation, required permits and approvals, design and<br />

construction implications of the environmental impacts, and considered all major costs of the project,<br />

so that a realistic cost estimate and schedule can be prepared.<br />

4.0 REFERENCES<br />

The following are the principal, but not the only, references to <strong>Federal</strong> legislation, codification,<br />

regulation and guidance of which the PMOC should have a good understanding as related to the<br />

project sponsor’s project work being reviewed under this <strong>Oversight</strong> Procedure (OP):<br />

4.1 United States Code<br />

• 49 U.S.C. § 5309<br />

• 49 U.S.C. § 5328(a)(3)<br />

• 42 U.S.C. §§ 4321-4347<br />

• 23 U.S.C. § 139<br />

• 49 U.S.C. § 303<br />

4.2 Regulations<br />

• 49 CFR Part 611<br />

• 23 CFR Part 771<br />

• 40 CFR Parts 1500-1508<br />

• 23 CFR Part 774<br />

5.0 PROJECT SPONSOR SUBMITTALS<br />

The PMOC shall obtain from the project sponsor the most current versions of the following:<br />

• Alternatives Analysis Report (prior to entry to PE)<br />

• MPO-adopted LRTP (prior to entry to PE)<br />

• Envirnmental documents (DEIS, EA, etc.)<br />

• Operating cost estimate for project<br />

• Capital cost estimate for project<br />

• Project schedule<br />

• New Starts submittals<br />

OP 32B Environmental Document (NEPA) Review for New Starts Projects<br />

Revision 0, June 2008<br />

Page 4 of 6