• Each document addresses the intended issues;<br />
• Assumptions made in each document are valid and proven;<br />
• Analytical methods used meet current professional standards;<br />
• The grantee’s review is by person’s competent in the field who capable of detecting and<br />
commenting on analytical errors;<br />
• Drawing and Configuration Control is designed to assure consistency throughout the fleet,<br />
including option orders;<br />
• The supplier’s QA program and the Grantee’s oversight will assure delivery of the vehicle “as<br />
designed”<br />
5.7 Quality Assurance<br />
The PMOC shall review the Grantee’s QA plan to assure the supplier’s QA will be performed under<br />
adequate surveillance, and will pay particular attention to assure the following:<br />
• The Grantee has qualified inspector(s) on site while production is underway;<br />
• Both the Grantee’s and the Supplier’s inspection services are independent enough of<br />
production and program management to assure issues are not suppressed;<br />
• Protocols are in place for dealing with discrepant materials and the grantee’s inspector has a<br />
voice in disposal of discrepant materials;<br />
• The Grantee’s requested delivery schedule provides sufficient time to assure supplier delays<br />
will not compromise vehicle quality.<br />
6.0 SCOPE OF WORK<br />
In addition to the reviews of submittals indicated above, the PMOC shall, as necessary, include<br />
recommendations for <strong>FTA</strong> to take corrective action with the Grantee.<br />
The checklists in Appendix A are provided as an assist to the PMOC.<br />
• Before making such a report, the PMOC shall discuss any noted or observed issues and<br />
possible corrective action with the grantee, and report the issues and intended corrective action<br />
concurrently to the <strong>FTA</strong>.<br />
• The PMOC shall pay special attention to the following key issues: This section might include<br />
a list of specific conditions that would require recommendation for corrective actions to the<br />
<strong>FTA</strong>. Such conditions might include:<br />
1. Schedule, issues potentially impacting schedule, and issues actually impacting<br />
schedule;<br />
2. Vehicle Safety Issues;<br />
3. Vehicle Reliability, Availability and Maintainability Issues;<br />
4. Issues impacting vehicle operability;<br />
5. Faulty or unreliable vehicle designs or systems;<br />
6. Known component or material deficiencies and availability of replacement parts;<br />
7. Other, such as payments to vendors (slow or no payments);<br />
OP26B Bus and Rail Vehicle Technical Review<br />
Revision 0, June 2008<br />
Page 5 of 6