4.1.2 Pre-Award Purchaser’s Requirements Review:<br />

(1) PMOCs must confirm that the Grantee/Sponsor has verified that the manufacturer’s<br />

bid specifications are in compliance with Grantee’s solicitation specifications.<br />

(2) PMOCs must also confirm that the Grantee has verified that the proposed/selected<br />

manufacturer is responsible and capable of building the bus to the<br />

Grantee’s/Sponsor’s solicitation specifications.<br />

4.1.3 Pre-Award FMVSS Requirements Review (for bus procurements):<br />

(1) PMOCs must confirm that the Grantee/Sponsor has obtained one of the following<br />

documents.<br />

• A letter from the bus manufacturer stating the information that is required for the<br />

FMVSS vehicle sticker will be provided or;<br />

• A letter from the bus manufacturer stating that the buses are not subject to<br />

FMVSS requirements.<br />

4.2 Post-Delivery Requirements Review:<br />

4.2.1 PMOCs must confirm that Grantee/Sponsor has completed a Post-Delivery review,<br />

before a vehicle title is transferred from the manufacturer to the Grantee/Sponsor, “or”,<br />

before vehicles are placed into revenue service, whichever is first.<br />

(1) The Grantee’s/Sponsor’s review period begins when the Grantee signs a formal<br />

contract with the selected manufacturer and ends before the title transfer or vehicle is<br />

put into revenue service.<br />

(2) For bus & rail vehicles, the Grantee/Sponsor may use the Pre-Award Buy America<br />

review documents to certify Post-Delivery compliance, if he is certain that none of<br />

the information has changed since the Pre-Award review. However, if the<br />

Grantee/Sponsor has any doubt, another review should be conducted.<br />

4.2.2 As with the Pre-Award review, for the Bus Post-Delivery review, PMOCs must confirm<br />

that the Grantee/Sponsor has completed separate certifications. Again, certifications must<br />

be kept in the Grantee’s/Sponsor’s files for future <strong>FTA</strong> reviews. The certifications<br />

required for Bus and Rail projects are;<br />

(1) Bus and Van projects:<br />

• Post-Delivery Buy America certification<br />

• Post-Delivery Purchaser’s Requirements certification<br />

• Post-Delivery FMVSS certification<br />

OP26A Buy America Review<br />

Revision 0, June 2008<br />

Page 6 of 14