FTA Oversight Procedures - Federal Transit Administration - U.S. ...

FTA Oversight Procedures - Federal Transit Administration - U.S. ... FTA Oversight Procedures - Federal Transit Administration - U.S. ...

25.10.2013 Views

candidates for the committee so that it can be formed and made operational in the following quarter. 3) Late changes in establishing the alignment have resulted in design delays. The TVA and Emergency Evacuation Plan (EEP) cannot be formally completed until the right of way is finalized. In the opinion of the PMOC, this delay should not affect commencement of revenue operations because the safety and security departments are participating in the design revisions on a real-time basis. 6.0 Conclusions and Recommendations This section should first present the major conclusions reached from the assessment as to the compliance of the SSMP with FTA Circular requirements and the adequacy of grantee adherence to the SSMP, as well as the overall project safety and security program. It should then present a numbered compilation of all recommendations contained in the other sections of the report. (Each recommendation should include a parenthetical reference to the section or subsection where the recommendation was made.) Appendices To simplify the reading of this Spot Report, it is recommended that certain material be placed in appendices at the end of the Report. Suggested appendices are: List of Documents Reviewed List of Personnel Interviewed List of Sites Visited Members of the SSMP Review Team (including PMOC, Recipient, and Project Staff, if any) Detailed Material in Support of Findings Detailed Project Description OP 22 Safety and Security Management Plan Review Revision 0, June 2008 Page F-3

APPENDIX G: ACRONYMS CPTED Crime Prevention Through Environmental Design CSM Construction Safety Manual EMP Emergency Management Plan FD Final Design FFGA Full Funding Grant Agreement FRA Federal Railroad Administration FTA Federal Transit Administration OMP Operations and Management Plan PHA Preliminary Hazard Analysis PMO Project Management Oversight PMOC Project Management Oversight Contractor PMP Project Management Plan RFMP Rail Fleet Management Plan SEPP Security and Emergency Preparedness Plan SITP System Integration Testing Plan SOP Standard Operating Procedure SSCP Safety and Security Certification Plan SSCVR Safety and Security Certification Verification Report SSI Security Sensitive Information SSMP Safety and Security Management Plan SSOA State Safety Oversight Agency SSPP System Safety Program Plan SSP System Security Plan SSWG Safety and Security Working Group TO Task Order TOM Task Order Manager TVA Threat and Vulnerability Analysis OP 22 Safety and Security Management Plan Review Revision 0, June 2008 Page G-1

candidates for the committee so that it can be formed and made operational in the<br />

following quarter.<br />

3) Late changes in establishing the alignment have resulted in design delays. The TVA and<br />

Emergency Evacuation Plan (EEP) cannot be formally completed until the right of way is<br />

finalized. In the opinion of the PMOC, this delay should not affect commencement of<br />

revenue operations because the safety and security departments are participating in the<br />

design revisions on a real-time basis.<br />

6.0 Conclusions and Recommendations<br />

This section should first present the major conclusions reached from the assessment as to the<br />

compliance of the SSMP with <strong>FTA</strong> Circular requirements and the adequacy of grantee adherence to the<br />

SSMP, as well as the overall project safety and security program. It should then present a numbered<br />

compilation of all recommendations contained in the other sections of the report. (Each recommendation<br />

should include a parenthetical reference to the section or subsection where the recommendation was<br />

made.)<br />

Appendices<br />

To simplify the reading of this Spot Report, it is recommended that certain material be placed in<br />

appendices at the end of the Report. Suggested appendices are:<br />

List of Documents Reviewed<br />

List of Personnel Interviewed<br />

List of Sites Visited<br />

Members of the SSMP Review Team (including PMOC, Recipient, and Project Staff, if<br />

any)<br />

Detailed Material in Support of Findings<br />

Detailed Project Description<br />

OP 22 Safety and Security Management Plan Review<br />

Revision 0, June 2008<br />

Page F-3

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!