B–60 Appendix B: Quality Assurance Resources<br />
SAMPLE<br />
CONSTRUCTION PROGRAM MANAGEMENT AND INSPECTION GUIDE (5/01/04)<br />
8.7 - Application of Quality Level Analysis in the Acceptance<br />
Determination<br />
In addition to evaluation for conformance with the Engineering Limits identified above, the QC<br />
<strong>and</strong> Acceptance test results for each Lot of Earthwork material will be continuously evaluated<br />
using Quality Level Analysis (QLA) for the following Quality Characteristics:<br />
▼ In-Place Density<br />
▼ In-Place Moisture Content<br />
The QLA for each Lot must indicate a Percent Within Limits (PWL) of 85% or higher, based<br />
upon the Targets <strong>and</strong> Specification Limits indicated in the Table below, in order for the Work to<br />
be accepted by Transportation Agency.<br />
Quality Level Analysis - Targets <strong>and</strong> Specification Limits<br />
Specification Limits<br />
Quality Characteristic Target LSL USL<br />
In-place Density 100% of W dm 95% of W dm None<br />
In-place Moisture Optimum (W mo ) W mo – 1% W mo + 1%<br />
9.0 – Other Relevant contractor QC Plans<br />
All Subcontractor <strong>and</strong> Producer QC activities for Earthwork are addressed within this QC Plan. There are no separate<br />
Subcontractor or Producer QC Plans included as Appendices at this time.<br />
In the event that separate Subcontractor or Producer QC Plans are submitted for Earthwork activity, this ABC<br />
Contractors Quality Control Plan for Section 1 – Earthwork will be amended to include such Plans <strong>and</strong> resubmitted for<br />
Transportation Agency approval.