SAMPLE<br />

8.6 – Application of Engineering Limits in the Acceptance<br />

Determination<br />

All work shall be performed to the lines, grades, cross-sections, dimensions, <strong>and</strong> material<br />

requirements set forth in the plans, specifications <strong>and</strong> this QC Plan. Each Lot of Earthwork<br />

material shall be uniform in character <strong>and</strong> reasonably close to the prescribed Target values <strong>and</strong><br />

within the Engineering Limits for each of the Quality Characteristics outlined in the tables<br />

below. If a QC or Acceptance test result for an individual Sublot falls outside of the Engineering<br />

Limits, the material contained in the Sublot represented by the failing test result will be reworked<br />

or disposed of in accordance with the procedures outlined in Section 7.6 above.<br />

8.6.1 – Backfill Material for Muck Excavation<br />

Appendix B: Quality Assurance Resources<br />

CONSTRUCTION PROGRAM MANAGEMENT AND INSPECTION GUIDE (5/01/04)<br />

Targets <strong>and</strong> Engineering Limits<br />

Lower Upper<br />

Engineering Engineering<br />

Material Type(s) Quality Characteristic Limit Target Limit<br />

Rock Excavate Maximum Rock Size - - 1 meter<br />

Soil Classification (AASHTO M145) A-3 or Portion of A-2 <strong>and</strong> A-1 per M1.02.0<br />

150 mm Sieve - Per SC 100<br />

50 mm Sieve 90 Per SC 100<br />

(AASHTO T311) 4.75 µm Sieve 20 PerSC 65<br />

75 µm Sieve 0 Per SC 12<br />

Plasticity Index (AASHTO T90) - - 6%<br />

Special Borrow Maximum Percentage of Wear - - 50%<br />

(M1.02.0) (LA Abrasion) (AASHTO T96)<br />

Maximum Dry Density (W dm ) SC – 5 kg/m 3 Per SC SC + 5 kg/m 3<br />

(AASHTO T180, Method D)<br />

Optimum Moisture Content (W mo ) SC - 2% Per SC SC + 2%<br />

(AASHTO T180, Method D)<br />

Maximum Lift Thickness - - 300 mm<br />

In-Place Density 95% W dm 100% W dm<br />

(AASHTO T310, Method B)<br />

In-Place Moisture Content W mo - 2% (W mo) W mo + 2%<br />

(AASHTO T310, Method B)<br />

B–51