B–42 Appendix B: Quality Assurance Resources<br />

SAMPLE<br />

CONSTRUCTION PROGRAM MANAGEMENT AND INSPECTION GUIDE (5/01/04)<br />

6.6 – Production QC <strong>Inspection</strong> Reporting<br />

All PQC inspection activities will be documented on the following st<strong>and</strong>ard QC <strong>Inspection</strong> Report<br />

Forms (IRFs):<br />

Form No. Form Title<br />

PQC-PPA Production QC - Pre-Production Audit Report<br />

PQC-IDR Production QC – Inspectors Daily Report<br />

A copy of the St<strong>and</strong>ard IRFs used for Production QC inspection of Earthwork materials is<br />

located in Appendix __ (see Note, page B–17).<br />

7.0 Field <strong>Management</strong><br />

The activities <strong>and</strong> procedures to be followed for QC during placement of Earthwork materials<br />

are as indicated below.<br />

7.1 – Schedule of Field Placement Operations<br />

ABC Contractors will provide Transportation Agency with a “Weekly Schedule of<br />

Earthwork Materials Placement Operations” on each Friday prior to the week of<br />

placement. A copy of the “Weekly Schedule of Earthwork Materials Placement<br />

Operations” is located in Appendix __ (see Note, page B–17). The weekly schedule of<br />

Placement Operations will identify the following:<br />

▼ Project Segment<br />

▼ Placement Location<br />

▼ Maximum Placement Depth<br />

▼ Intended Placement Locations (Roadway, Station Limits)<br />

▼ Material Type(s)<br />

▼ Estimated Placement Quantities<br />

▼ Material Source(s)<br />

ABC Contractors will track the actual placement quantities on a daily basis <strong>and</strong> maintain a “Record<br />

of Earthwork Placement” for each week. Copies of the “Record of Earthwork Placement” will be<br />

made available to Transportation Agency.<br />

7.2 – Field Placement Facilities <strong>and</strong> Equipment<br />

ABC Contractors will utilize conventional facilities <strong>and</strong> equipment for the placement of all<br />

Earthwork materials. The major types of facilities <strong>and</strong> equipment to be utilized for Earthwork<br />

placement are summarized below for each type of Earthwork Item.