5.4.5 – Backfill Material for Pipes*<br />

Quality<br />

QC Sampling <strong>and</strong> Testing Requirements<br />

Sublot Size/<br />

Test Point of Sampling<br />

Characteristic Test Method(s) Lot Size Frequency Sampling Method<br />

Total Quantity of<br />

AASHTO T11 Backfill Material 1 Sample/ From In-Place R<strong>and</strong>om<br />

Gradation AASHTO T27 Type / Source / 1,000 m 3 Lift of Backfill T2, T248<br />

Project Segment<br />

Maximum Dry AASHTO T99 Total Quantity of<br />

Density <strong>and</strong> (Method C) Backfill Material 1 Sample/ From In-Place R<strong>and</strong>om<br />

Optimum AASHTO T180 Type / Source / 1,000 m 3 Lift of Backfill T2, T248<br />

Moisture Content (Method D) Project Segment<br />

Total Quantity of<br />

Maximum Backfill Material Minimum From In-Place R<strong>and</strong>om<br />

Stone Size Visual/Tape Type / Source / 4/Lift/Day Lift of Backfill Visual<br />

(< 75 mm) Project Segment<br />

Total Quantity of<br />

Maximum Rod/Grade Backfill Material Minimum From In-Place R<strong>and</strong>om<br />

Lift Thickness Stake Type / Source / 4/Lift/Day Lift of Backfill Visual<br />

(< 150 mm) Project Segment<br />

Gravel Borrow:<br />

1 Sample/100 m<br />

of Trench, but<br />

not less than<br />

1/Lift/Day<br />

In-Place Total Quantity of From<br />

Density <strong>and</strong> AASHTO T310 Backfill Material Ordinary Borrow: Compacted R<strong>and</strong>om<br />

Moisture Content (Method B) Type / Source / 1 Sample/100 m Backfill T310<br />

(Per Targets) Project Segment of trench, but<br />

not less than<br />

1/Placement<br />

Location/Day<br />

(*) Backfill Material for Pipes will include Gravel Borrow <strong>and</strong> Ordinary Borrow to be<br />

placed as follows:<br />

Gravel Borrow – Gravel Borrow shall be used for bedding <strong>and</strong> backfilling of pipe<br />

to a point 600 mm above the top of pipe.<br />

Ordinary Borrow – Ordinary Borrow shall be used to backfill the remaining<br />

depth of trench from the top of the Gravel Borrow to the top of the finished<br />

subgrade.<br />

Appendix B: Quality Assurance Resources<br />

CONSTRUCTION PROGRAM MANAGEMENT AND INSPECTION GUIDE (5/01/04)<br />