14.10.2013 Views

Construction Program Management and Inspection Guide

Construction Program Management and Inspection Guide

Construction Program Management and Inspection Guide

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Appendix F: Examples of Reporting Practices<br />

CONSTRUCTION PROGRAM MANAGEMENT AND INSPECTION GUIDE (5/01/04)<br />

Changes, Extra Work, <strong>and</strong> Time Extensions<br />

Report Items<br />

The final contract cost is expected to exceed the contract bid<br />

amount by 26 percent.<br />

The final project cost will be approximately $700,000—an<br />

overrun of about 10 percent. Major items making up the<br />

overrun are: (list followed)<br />

The final project cost overran the original authorization by<br />

approximately 22 percent. The majority of this overrun was<br />

due to encountering a very wet subgrade that required a<br />

considerable amount of subexcavation <strong>and</strong> importing of<br />

embankment materials. Overruns also occurred in temporary<br />

striping, stripe removal, cement-treated base <strong>and</strong> asphalt<br />

paving.<br />

Several change order documents were discussed <strong>and</strong> found<br />

satisfactory.<br />

There have been three COs to date on this project. CO No. 1<br />

was reviewed in detail. The file contained adequate<br />

justification for making changes on the project as directed by<br />

CO No. 1.<br />

The slide area mentioned in a previous report has moved<br />

enough to cause displacement of the new pavement surface. If<br />

movement continues, stabilization work may be required. Any<br />

corrective work could best be h<strong>and</strong>led separately from this<br />

contract.<br />

The material had to be removed from the deck surface. This<br />

requirement had not been specifically noted in the plans or<br />

special provisions. The contractor may request extra<br />

compensation for this work.<br />

The contractor has submitted a request for a time extension,<br />

which is currently being reviewed.<br />

Comments<br />

Since early notice of the overrun will probably not be used for<br />

fiscal control, this comment is of little value without more<br />

explanation.<br />

Specific comments such as this are more of value than the<br />

general comment noted above. If possible at this time, the<br />

FHWA position regarding the overruns should be reported.<br />

This comment goes a step further <strong>and</strong> identifies the reason for<br />

the major overrun as well as the items involved. This level of<br />

detail is desirable.<br />

This discussion may have been of value at the time, but the<br />

failure to be specific makes the comment meaningless to<br />

anyone other than the principals involved.<br />

This specific comment is much more appropriate than the one<br />

above.<br />

An anticipated future problem has been identified. This note,<br />

which serves to alert readers of the possible need for action,<br />

also contains FHWA’s suggestion for contracting the work.<br />

The possible need for change orders or claims on work, which<br />

has already been accomplished, should also be noted.<br />

This comment concerning a time extension is of little value<br />

without additional information. Since the discussion is<br />

appropriate, it should have been exp<strong>and</strong>ed.<br />

F–11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!