D–16<br />

Appendix D: <strong>Inspection</strong>s-in-Depth<br />

CONSTRUCTION PROGRAM MANAGEMENT AND INSPECTION GUIDE (5/01/04)<br />

Examine those physical features of completed work that are<br />

visible:<br />

▼ Apparent workmanship <strong>and</strong> degree of care given by the<br />

quality control <strong>and</strong> acceptance process.<br />

▼ Visual lines <strong>and</strong> grades.<br />

▼ Straightness of overhangs, curb chamfers, railings.<br />

▼ Uniformity of the surface texture.<br />

▼ Surface drainage <strong>and</strong> outfalls.<br />

▼ Uniformity of position of roller-bearing devices.<br />

▼ Conformance of expansion plates to the grades of the<br />

deck <strong>and</strong> required gap.<br />

▼ Final cleanup; the removal of temporary supports,<br />

detour facilities, <strong>and</strong> debris.<br />

Review field office documentation:<br />

▼ Test reports.<br />

▼ Pay quantities. Verify that calculations meet st<strong>and</strong>ard<br />

specification requirements.<br />

▼ Delivery records (invoices, delivery tickets, reports, etc.)<br />

on incorporated materials.<br />

▼ Verify that test <strong>and</strong> inspection reports covering<br />

materials incorporated in the minor structures<br />

document compliance with the contract.<br />

Prestressed Concrete Members<br />

Review during construction:<br />

▼ Procedures for prestress plant inspection; verify<br />

compliance on current project.<br />

▼ Erection sequence <strong>and</strong> equipment requirements for<br />

lifting; verify compliance with the approved erection<br />

plan.<br />

▼ Bearing seats at correct elevation <strong>and</strong> alignment.<br />

▼ Inspect beams for correct camber, length, alignment,<br />

<strong>and</strong> damage.<br />

Temporary Structures<br />

Ensure:<br />

▼ Shop drawings or plans are signed by a registered<br />

professional engineer.<br />

▼ Structure meets plan requirements for minimum<br />

roadway width, vertical clearance, <strong>and</strong> minimum<br />

opening size.<br />

Subbase <strong>and</strong> Base<br />

▼ Verify if this should include subgrade.<br />

▼ Verify that the quality control <strong>and</strong> acceptance<br />

procedures maintain effective inspection at all points of<br />

work.<br />

Subgrade<br />

▼ Verify procedures used to document subgrade<br />

preparation for grade, cross-section, surface uniformity,<br />

moisture content, density, <strong>and</strong> correction of soft spots<br />

prior to placing subsequent pavement structure.<br />

▼ Verify subbase <strong>and</strong> base as-constructed <strong>and</strong> material<br />

properties.<br />

On projects where the final thickness of the pavement<br />

structure is established from test results obtained from the<br />

constructed subgrade, verify the frequency <strong>and</strong> adequacy of<br />

the on-site sampling <strong>and</strong> testing; check that the<br />

recommended thickness is in conformity with the State’s<br />

design criteria for thickness of flexible pavements.