SECTION 5<br />

(viii) A statement showing the extra and substituted items submitted by the contractor, and the<br />

payments received against them, items pending for sanction/decision by the <strong>Department</strong>,<br />

broad details of the bank Guarantees, indicating clearly their validity periods, broad details of<br />

the insurance policies taken by the contractor, if any, the advances received and adjusted.<br />

(ix) Progress photographs, in colour, of the various items/components of the work done upto<br />

date, to indicate visually the actual progress of the work.<br />

(x) Quality assurance and quality control tests conducted during the month, with the results<br />

thereof.<br />

(2) The progress report submitted by the contractor shall be checked and certified by the Junior<br />

Engineer and the Assistant Engineer, and has to be reviewed by the Executive Engineer and the<br />

Superintending Engineer, over their dated signatures.<br />

(3) All works costing Rs. 15 crores and above, and any work of unique importance and character<br />

irrespective of the value of the work, should have videography undertaken at various stages of<br />

construction right from the day of start of work to date of completion/occupation, covering all major<br />

events, inspections, visits by dignitaries, etc.<br />