APPENDIX 31A<br />

To<br />

APPENDIX – 31A<br />

(Reference para 33.1.1)<br />

(Added vide OM/MAN/221)<br />

PROFORMA FOR SHOW CAUSE TO THE CONTRACTOR REGARDING COMPENSATION<br />

UNDER CLAUSE 2<br />

Name & Address of the contractor<br />

………………………………………………….<br />

………………………………………………….<br />

Sub: Show Cause for delayed completion/likely to be delayed completion of work ........................ under<br />

Agreement No …………. ………..<br />

Dear Sir (s),<br />

The date of completion for the above mentioned work was/is ………….. as stipulated in the agreement<br />

number ………………………………………… for the work …………………………......<br />

Extensions of time for completion of the above mentioned work was extended by the Engineer-in-<br />

Charge vide his letter no. ............ up to ……………. under clause 5 of the said agreement without prejudice<br />

to the right of the Government to recover compensation in accordance with the provisions of Clause 2 of<br />

the said agreement.<br />

The work entrusted to you under the agreement referred above could not/unlikely to be completed<br />

within stipulated/extended date of completion due to your wrongful delay or suspension of work or slow<br />

progress of work or because of reasons within your control. The work has finally been completed<br />

on………… /cannot be completed within stipulated/extended date of completion. Therefore, under the<br />

provisions of clause 2 of the above said agreement you have rendered yourself liable to pay compensation.<br />

Therefore, I, in exercise of the powers conferred on me by the aforesaid agreement, for and on behalf<br />

of the President of India, hereby give you show cause within ……………. to my satisfaction that why<br />

compensation should not be imposed upon you under the provisions of clause 2 of said agreement for<br />

delayed/likely to be delayed completion of the work. Please note that in case no cause is shown by you<br />

within the stipulated period or the cause shown is not to my satisfaction, I shall take such actions against<br />

you as are contemplated under Clause 2 there under of the said agreement without further notice.<br />

419<br />

Yours faithfully,<br />

(........................................)<br />

Superintending Engineer<br />

Note: Strike out whichever is not applicable. Notice may be modified suitably intending to impose<br />

compensation when tendered value of the item or group of items of work for which a separate<br />

period of completion is originally given.