418 APPENDIX 31<br />

To<br />

APPENDIX – 31<br />

(Reference para 29.12)<br />

(Modified vide as per OM/MAN/181 & 221)<br />

PROFORMA FOR INTIMATING THE CONTRACTOR REGARDING COMPENSATION<br />

UNDER CLAUSE 2<br />

Name………………………………………..<br />

Address of the contractor ……………......<br />

……………………………………………….<br />

………………………………………………<br />

Subject: Intimation regarding levy of compensation under clause 2<br />

Dear Sir (s),<br />

The date of completion for the above mentioned work was ………….. as stipulated in the agreement<br />

number …………………………………………..for the work of………………………………<br />

Extension of time for completion of the above mentioned work was extended by the Engineer-in-<br />

Charge vide his letter no. up to ……………. under clause 5 of the said agreement without prejudice to the<br />

right of the Government to recover compensation in accordance with the provisions of Clause 2 of the<br />

said agreement.<br />

The work has finally been completed/determined (strike out whichever not applicable) on …………<br />

. You were issued show cause vide this office letter no………………….. to explain why compensation<br />

not be imposed upon you under the provisions of clause 2 of said agreement for delayed completion of<br />

the work.<br />

Your reply vide letter no. ……………… received in response to show cause has been considered<br />

carefully. (Reasons for not agreeing with hindrances as claimed by the contractor and total delay on part<br />

of contractor to be indicated in brief). After taking into consideration all the facts & circumstances I have<br />

come to the conclusion that you are solely responsible for delay of ...... months ...... days.<br />

In exercise of the powers conferred on me under Clause 2 of the agreement, I ………….. the<br />

Superintending Engineer decide and determine that you are liable to pay Rs…………… as and by way of<br />

compensation as stipulated in Clause 2 of the agreement. The said amount of compensation is hereby<br />

levied on you for the period of ……………… and at the rate of …………. as determined by me on the<br />

tendered amount of the work shown in the agreement and you are hereby called upon to pay the same to<br />

the Government within ……………….(here mention the period) failing which the said amount shall be<br />

adjusted or set-off against any sum payable to you under this or any other contract with the Government.<br />

Yours faithfully,<br />

(................................)<br />

Superintending Engineer