APPENDIX 17<br />

APPENDIX – 17<br />

[Reference para 15.9(7)]<br />

STANDARD SCHEDULE OF CONTRACT PERIODS FOR BUILDINGS WORKS<br />

Sl. No. Number of Storeys Time Period (Months)<br />

1. Upto 4 Storeys 8 to 12<br />

2. Beyond 4 and upto 6 storyes 12 to 15<br />

3. Beyond 6 Storeys 16 to 21<br />

(Note:- Basement may be treated equivalent to one storey)<br />

Time may be varied suitably due to following factors.<br />

(a) Rainy season and inundated conditions<br />

(b) Depth of subsoil water<br />

(c) Special features of the building<br />

(d) Scattered/concentrated works<br />

(e) Congested site<br />

(f) Type of foundation<br />

(g) Urgency/Importance of the work<br />

(h) Extent of Mechanization involved<br />

(i) Logistics available in area.<br />