292 SECTION 53<br />

(5) Where some observation paras have been brought to the notice of the Superintending Engineer/<br />

Chief Engineer, they should send their comments/replies after personal inspection in case the<br />

work is located at the same station/headquarter. For outside works, the Superintending Engineer/<br />

Chief Engineer can take the assistance of the Assistant Engineer(QA)/Superintending Engineer<br />

(P&A) in order to ensure that the replies are sent within 4 weeks from the date of receipt of the<br />

Inspection Reports/letters from the Superintending Engineer (QA)/Chief Engineer (CSQ).<br />

(6) Notwithstanding the above, serious irregularities/defaults, over-payments, shortages, frauds like<br />

wrong certification, or wrong report of rectification of defects etc. may be referred to the Chief<br />

Engineer (Vig/CVO) immediately by the Chief Engineer (CSQ).<br />

53.15 Action in Divisions on the Inspection Report of Core Wing/Regional QA unit<br />

Proper attention by the field units to the concept of Quality Assurance as dealt in para 53.1 above and<br />

a continuous check over process control should as a matter of fact give no opportunity to the Core Wing<br />

to bring out any shortcoming in quality related aspects of the work. Following action shall be taken by the<br />

Executive Engineer on receipt of the Inspection Report from the Core Wing/Regional QA unit:<br />

(i) It should be immediately brought to the notice of the Assistant Engineer and the Junior Engineer in<br />

charge of the work.<br />

(ii) The following further action should be taken:<br />

(a) The various observations involving the contractor’s work or any other obligation of the contractor<br />

shall be brought to the notice of the contractor through the Site Order Book.<br />

(b) The work should be checked up for defects similar to the ones observed at other locations,<br />

and all such findings also brought to the notice of the contractor suitably as above. It should be<br />

ensured that similar defects do not recur in further work.<br />

(c) Wherever the defects are rectifiable, action should be taken for their rectification, simultaneously<br />

ensuring that such works are not placed in a position beyond rectification. No further work<br />

shall be done at that location till the defects are rectified. Also to investigate why such defects<br />

were not arrested by process control quality assurance set-up in the Divisional Office in the<br />

first instance.<br />

(d) For items of observations not involving the contractor’s work/obligations, the Executive Engineer<br />

shall ensure that due action is taken in time.<br />

(e) Wherever any para is referred to the Superintending Engineer/Chief Engineer, the Executive<br />

Engineer should send an action taken report to the Superintending Engineer on priority.<br />

(f) The Executive Engineer concerned shall take action on the observations, and send compliance<br />

report on rectification of defects/deficiencies to the QA Unit within a period of 4 weeks from the<br />

date of receipt of the Inspection Report.<br />

(iii) There should be concerted efforts on the part of the field units as well as the QA cell to comply with<br />

the observations of the QA cell, and finally settle all the paras during the progress of the work itself<br />

so that the bill for the work is finalised in time. Such observations should not be allowed to linger on<br />

indefinitely.<br />

53.16 Action in Circle Office on Inspection Reports of QA units<br />

Following action shall be taken by the Superintending Engineer on receipt of the Inspection Report<br />

from the Core Wing/Regional QA unit:<br />

(1) To analyze the reason for occurrence of the reported defects/shortcomings as to how the QA setup<br />

in Divisional and Circle levels failed to arrest them in the first instance, and taking action including<br />

seeking explanation from the concerned field officers.<br />

(2) Watching the compliance of the observations by the Executive Engineer and his Assistant<br />

Engineers/Junior Engineers, and to ensure that replies to the Inspection Reports of the Core Wing<br />

are sent expeditiously.<br />

(3) On paras referred to the Superintending Engineer/Chief Engineer by the QA Wing, they shall not<br />

endorse the reply of the Executive Engineer as it is. They shall duly satisfy themselves about the<br />

same before sending their comments/reply to the QA unit.