288 SECTION 53<br />

(xv) The Executive Engineers should ensure that the Assistant Engineers and Junior Engineers, as<br />

well as the contractor’s supervisors in-charge are fully aware of the specifications and method of<br />

execution of any new/fresh item of work to be taken up in the next 2 weeks. The Assistant Engineers/<br />

Junior Engineers/Supervisors should ensure that this important aspect is not overlooked. The<br />

Junior Engineers/Assistant Engineers shall carry the required field testing instruments as per<br />

Annexure II to ensure on site quality assurance check on a regular basis, and to enable the senior<br />

officers to conduct checks during their site visits.<br />

(xvi) Checklist<br />

(a) As and when any important item is taken up for execution, the Junior Engineer/Assistant<br />

Engineer should go through the specifications and invariably make a checklist. This checklist<br />

should be got approved from the Executive Engineer, and should be shown to the inspecting<br />

officers. The important items inter-alia include foundation work, including reinforcement and<br />

shuttering, brickwork, cast-in-situ mosaic flooring, doors & windows, plumbing, including water<br />

supply pipe lines, roof treatment, earth filling etc. which are a few illustrative items for checklist<br />

purpose.<br />

(b) Sample checklists for items of concrete for raft, columns/beams/slabs, water supply lines,<br />

brickwork and plastering are given in Annexure IV for guidance.<br />

(xvii) To avoid dampness and leakage, the Executive Engineers shall ensure that necessary tests are<br />

carried out for proper slopes of canopies, chajjas, terracing, drainage arrangements, water tightness<br />

of expansion joints, joints in the water supply, drainage and sanitary works before these are covered/<br />

concealed, and also ensure rectification of defects noticed.<br />

(xviii) The Executive Engineers shall ensure availability of the required test equipments for field tests, as<br />

well as an updated copy of specifications, copies of agreement at sites of works.<br />

53.8 Quality Assurance team at Circle level<br />

(1) The Quality Assurance team with the Superintending Engineer of the Circle as its head will comprise<br />

the Assistant Engineer (along with his Junior Engineer for laboratory work), whose main job is<br />

quality assurance. In order that the role of the Assistant Engineer (QA) is effective in the process<br />

of Quality Assurance, the following points are essential:<br />

(i) The periodicity of visit of works should be such that the process control at various stages is<br />

possible.<br />

(ii) There should be minimum delay between inspection of work and communication of inspection<br />

report to the field formation.<br />

(iii) The Assistant Engineer (QA) should carry out his tasks in a work that relates operationally to<br />

the quality specifications and standards laid down for the work, and to the control actions that<br />

can be applied to the construction process. Thus the Assistant Engineer (QA) should assess<br />

those aspects which are important to the overall quality of the finished work.<br />

(2) The functions of the Quality Assurance team at Circle level are to check the compliance of Quality<br />

Assurance system by the field units, to locate the lapse/deficiency in the implementation of the<br />

Quality Assurance Plan, and to guide the field engineers in quality related aspects of the work. For<br />

this purpose:<br />

(i) Every Assistant Engineer (QA) should carry out minimum four visits to works every month.<br />

(ii) The Assistant Engineer (QA) should prepare his program and take approval of the<br />

Superintending Engineer. The program should be sent to site in advance of inspection.<br />

(3) Such inspections by the QA team shall, however, not absolve the responsibility of the Junior<br />

engineer/Assistant engineer/Executive Engineer for accepting only quality work from the contractor.<br />

(4) The following norms have been decided for inspection to be carried out by the Assistant Engineer<br />

(QA) of the Circle Office:<br />

(i) Construction works costing more than Each work to be inspected at least<br />

normal tender acceptance powers of the thrice during currency of work.<br />

Superintending Engineer