SECTION 46<br />

SECTION 46<br />

STOCK TAKING<br />

46.1 Physical verification of stores<br />

(1) The Executive Engineers are to have stock taken through out their Divisions at least once a year.<br />

It is not necessary that all the stocks of a Division or even of a Sub-Division should be checked<br />

and counted at the same time, but the date on which articles are taken stock of should be entered<br />

in the stores returns. The stores should be counted by an officer not below the rank of Assistant<br />

Engineer, who is not the custodian, the ledger keeper or the accountant of the stores.<br />

(2) Physical verification should be made in the presence of the authority responsible for the custody<br />

of the stores or of a person deputed by him. If such an authority fails to be present during physical<br />

checking of stores or fails to depute a person, the verification should be carried out in the presence<br />

of another officer who is not in-charge of the stores.<br />

(3) The results of verification of stock should be reported to the Divisional Officer for orders, but as<br />

soon as a discrepancy is noticed, the book balance must be set right by the verifying officer,<br />

treating surplus as a receipt and a deficit as an issue, with a suitable remark.<br />

(4) The shortages and damages, as well as unserviceable stores, should be reported immediately to<br />

the authority competent to write-off the loss.<br />

(5) The verification of road metal and materials charged direct to works will also be done in the manner<br />

prescribed above.<br />

46.2 Physical verification of MAS account and dismantled materials account<br />

Apart from the stock, dismantled materials stores and materials at site account are also to be checked<br />

in the same manner every year and certificates recorded in the registers.<br />

46.3 Physical verification of T&P<br />

In case of Tools and Plants, the stocktaking should be done every 6 months ending 31st March and<br />

30th September in the same manner as stated above, and certificates of physical verification recorded<br />

thereon.<br />

46.4 Report on physical verification<br />

The report about the required stocktaking and physical verification and certification thereof should be<br />

reported immediately to the Superintending Engineer.<br />