228 SECTION 35<br />

(2) The decretal amount of the claim vide item (i) above should be debited in all cases to the works<br />

concerned, and the charges referred to in item (ii) above to the sub-head “Establishment<br />

Contingencies” of the executing department. As regards item (iii), the amount should generally be<br />

borne by the department on whose behalf the work is undertaken on the ground that the action of<br />

the executing department was as agent and taken in the interests of the work.<br />

(3) When, however, it is established that the law suit has been caused by a deliberate act of an<br />

employee of the agent department for his personal gain, the charges should be adjusted by recovery<br />

from the individual concerned or by debit against the merits of each case. Such cases should be<br />

submitted to the Government of India for their orders.<br />

35.22 General<br />

(1) In order to enable the Executive Engineers to put up proper defence of the case, it is necessary<br />

that as and when the Executive Engineers hand over charge of the Division, or transfer arbitration<br />

cases/works, they should, unless all the facts and arguments are already explained in the written<br />

counter statement of facts, prepare and place on record a self-contained note giving all the facts<br />

of the case and detailed comments on the claims.<br />

(2) In order to enable speedy disposal of cases, the Executive Engineers should not ask for<br />

adjournment to the extent possible.<br />

(3) The Executive Engineer should always maintain a separate file so far as the disputes that have<br />

cropped up on the work during the progress of the work. In case of his transfer or relinquishing<br />

charge due to any reason, he should leave a self contained note on the file at the time of his<br />

handing over charge, giving full background of all the disputes that have cropped up during the<br />

time of his incumbency, various developments thereon and the orders passed with due reference<br />

to the connected files. This should form a necessary and essential feature of all the handing over<br />

notes. Suitable method and procedure should be devised in the Divisional Office by which such<br />

files are carefully preserved and become available at a later stage to the Executive Engineer who<br />

is required to defend the case.<br />

(4) The transferred Executive Engineers should make a comprehensive note about the pending<br />

claims of all the contractors for works in progress or completed in their time, except those where<br />

counter statements of facts have already been prepared. The note should indicate the admissibility<br />

or otherwise of each claim and the orders of competent authority. The note along with attested<br />

true copies of important letters mentioned therein should be handed over to their successors/<br />

other Divisions.<br />

(5) It should be made a rule in the Divisional Office that all the drawings issued with the NIT, and<br />

those subsequently followed for execution of works are properly preserved and kept along with<br />

the contract documents. It should be ensured by the Executive Engineer that suitable and adequate<br />

arrangements are made in his Division regarding preservation of all important documents, registers<br />

etc. Besides others, a list of all such records should be prepared and kept handy so that correct<br />

position of each case may be known to the Executive Engineer who is required to conduct the<br />

case, to enable him to do so on proper lines.<br />

(6) The arbitration cases should not be considered as legacy of old and defunct Divisions handed<br />

over to subsequent Executive Engineers. These should, on the other hand, be given due importance<br />

and dealt with on priority basis at all stages till these are finally disposed of.<br />

(7) One of the important documents for defence in an arbitration case is the agreement. It is essential<br />

that a copy of the Superintending Engineer’s orders conveying his decision on recovery of<br />

compensation and copies of sanctioned extra, substituted and deviated items and sanctions to<br />

extension of time, etc. are attached to the original agreement so that these are readily available<br />

during the hearings of the arbitration case. It would be better if these papers are got signed by the<br />

contractor as far as possible, so that any claim on these issues can be refuted before the Arbitrator.