24.10.2012 Views

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

224 SECTION 35<br />

(4) The Executive Engineer should make payment to the contractor in terms of the award within a<br />

period of 30 days from the receipt of acceptance of award from the competent authority, and<br />

intimate the actual date of payment of award to the contractor.<br />

(5) The payments made towards arbitration awards shall be charged to the work.<br />

(6) In all arbitration cases where awards of the Arbitrator go against the <strong>Department</strong> (whether by<br />

upholding the claims of the contractors or by rejecting the counter claims of the <strong>Department</strong>),<br />

detailed reasons and lapses, if any, on the part of concerned officials due to which the awards<br />

have gone against the <strong>Department</strong>, should be gone into in detail by the Chief Engineer concerned.<br />

The Chief Engineer should send his recommendations to the Director General (<strong>Works</strong>) on the<br />

issue of fixing of responsibility and for taking action against the officers, wherever necessary.<br />

(7) The Chief Engineers will keep statistics of all such cases for the information of Government<br />

whenever required.<br />

(8) The arbitration award means the total award including the interest awarded by the Arbitrator. The<br />

amount of such interest is to be worked out upto the date specified in the award. Therefore, the<br />

amount of the interest has to be taken into consideration while deciding the authority competent to<br />

accept the award. However, in case no fixed date is specified in the award and the interest is to be<br />

paid upto the date of actual payment of award amount to the contractor, the likely date of such<br />

payment may be taken into consideration. There may be a situation that after acceptance of the<br />

award by the competent authority, the actual payment to the contractor gets delayed beyond the<br />

anticipated date due to some unavoidable circumstances, and the amount of interest increases to<br />

an extent that the total amount of award exceeds the power of acceptance of the authority that<br />

accepted the award. In such cases, the payment may be made to the contractor as early as<br />

possible, and the case may be submitted to the authority competent to accept the increased<br />

amount of award for ex-post facto approval.<br />

35.16 Setting aside of the award<br />

(1) The question of challenging the arbitral award in a Court of law should be considered very carefully.<br />

Under section 34 of Arbitration and Conciliation Act, 1996, there are very few grounds available to<br />

challenge the arbitral award as follows:<br />

(a) The party making the application furnishes proof that:<br />

(i) a party was under some incapacity, or<br />

(ii) the arbitration agreement is not valid under the law to which the parties have subjected it<br />

or, failing any indication thereon, under the law for the time being in force, or<br />

(iii) the party making the application was not given proper notice of the appointment of an<br />

Arbitrator or of the arbitral proceedings or was otherwise unable to present his case, or<br />

(iv) the arbitratal award deals with a dispute not contemplated by or not falling within the terms<br />

of submission to arbitration, or it contains decision on matters beyond the scope of<br />

submission to arbitration, provided that, if the decision on matters submitted to arbitration<br />

can be separated from those not submitted, only the part of the arbitral award which contains<br />

decisions on matters not submitted to arbitration may be set aside, or<br />

(v) the composition of the arbitral tribunal or arbitral procedure was not in accordance with the<br />

agreement of the parties, unless such agreement was in conflict with a provision of this<br />

Part from which the parties cannot derogate, or failing such agreement, was not in<br />

accordance with this Part, or<br />

(b) The Court finds that:<br />

(i) the subject matter of the dispute is not capable of settlement by the arbitrator under the law<br />

for the time being in force, or<br />

(ii) the arbitrate award is in conflict with the public policy of India.<br />

(2) An application for setting aside an arbitration award may not be made after 3 months have elapsed<br />

from the date on which the party making that application had received that arbitral award or from

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!