24.10.2012 Views

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

SECTION 35<br />

SECTION 35<br />

ARBITRATION AND LITIGATION CASES<br />

35.1 Dispute Redressal Committee (Modified as per OM/MAN/233)<br />

In order to drastically reduce the number of cases filed by the contractors for arbitration, and to redress<br />

the disputes with the contractor in accepting any decision of a competent authority on any matter relating<br />

to a contract there shall be a Standing Committee, convened by the Additional Director General, for each<br />

Zone in the Region, comprising of the following Members:<br />

(A) For total claims more than Rs. 25.0 lakh<br />

(a) One Chief Engineer (Chairman) (other than under whose jurisdiction work falls)<br />

(b) Superintending Engineer(TLCQA)/ Director works.<br />

(c) One Superintending Engineer (other than under whose jurisdiction work falls)<br />

(d) The SE in-charge of the work shall present case before DRC but shall not have any part<br />

in decision making.<br />

(B) For total claims up to Rs. 25.0 lac<br />

(a) Superintending Engineer (TLCQA) / Director works, (Chairman)<br />

(b) Two Executive Engineers other than EE under whose jurisdiction the work falls.<br />

(c) The Executive Engineer in-charge of the work shall present the case before DRC but<br />

will not have any part in decision making.<br />

(2) In the first instance, the Executive Engineer, Superintending Engineer, or the Chief Engineer shall<br />

positively give his decision on any matter relating to the contract, for which he is competent to do<br />

so. If the decision so given is not acceptable to the contractor due to any legitimate reason, efforts<br />

shall be made to reason with the contractor to arrive at a consensus that is reasonable and legitimate<br />

under the terms and conditions of the contract. If, however, no consensus can be reached, the<br />

matter shall be referred to the next higher authority, and if no consensus can be reached at that<br />

level too, then the Chief Engineer shall refer the matter to the Committee for adjudication. In other<br />

words, cases shall be referred to the Committee only after exhausting all other remedies available<br />

with the officers of the department who are a party to the contract.<br />

(3) The Superintending Engineer and his Executive Engineer, who are parties to the contract under<br />

dispute, shall present the case of the department before the Committee, alongside the contractor<br />

who shall present his case. The Committee shall hear both the parties, and suggest an amicable<br />

and legitimate solution to the problem, based on the principle of equity and natural justice. If the<br />

same is acceptable to both the parties, it shall be accepted by the officer in the department under<br />

whose competence the matter falls, and conveyed for implementation. If, however, the Committee<br />

fails to resolve the issue, the decision taken by the competent authority of the department in the<br />

matter would stand. It would then be up to the contractor to either accept it, or to apply for arbitration<br />

under the provisions of the contract.<br />

(4) Wherever such a Dispute Redresal Committee is constituted in a Region, suitable provisions for<br />

the same should be made part of NIT that ADG in charge shall be the competent authority<br />

to constitute DRC comprising members mentioned above. This shall be incorporated in<br />

the Schedule of CPWD 7/8, and shall form a part of the contract.<br />

The DRC shall have to give decision on the claims of contractor or department within three<br />

months of receipt of reference. If no decision is given by DRC within three months then<br />

claimant shall be at liberty to seek appointment of arbitrator.<br />

In case, either department or contractor is not satisfied with the decision of DRC, each can<br />

seek appointment of arbitrator.<br />

The contractor shall only be entitled to invoke the arbitration clause after exhausting the remedy<br />

available under the Dispute Redressal Committee.<br />

35.2 Application of arbitration clause 25 of standard contract form<br />

(1) Clause 25 of the standard Forms No. CPWD 7 and 8 and other relevant clauses in Forms no.<br />

CPWD 9, 11, 11 A and 12, provides for appointment of an Arbitrator in case of questions and<br />

disputes relating to certain matters, specified therein arising at any stage, whatever, between the<br />

parties. This, however, does not apply to action taken under following clause where the decision<br />

of the specified officer is final to the extent given below:<br />

217

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!