24.10.2012 Views

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

SECTION 33<br />

unskilled male mazdoor’ notified by the Ministry of Labour and that notified by the Local<br />

Administration, will be collected by the Superintending Engineer (TAS). He will work out the indices<br />

relevant to each month as per definition given in the sub clause and communicate to all the ADGs,<br />

Chief Engineers and Superintending Engineers, who would arrange to circulate these figures to all<br />

the Executive Engineers under their jurisdiction.<br />

(5) Copies of all sanctions issued by the Executive Engineer shall be sent to his Superintending<br />

Engineer and to his Chief Engineer also if the tender for the work was accepted by the Chief<br />

Engineer.<br />

33.11 Clause 12 of Forms no. CPWD 7 & 8<br />

(1) Under this clause the Engineer-in-charge has powers to make any alterations in, omission from,<br />

addition to or substitution for the original specifications, drawings, designs and instructions.<br />

(2) The Engineer-in-charge is empowered under this clause to give necessary instructions to the<br />

contractor, and the contractor is bound to carry out the work in accordance with such instructions,<br />

but the following three conditions should be satisfied in the issue of such instructions:<br />

(i) Instructions must be given before any additional or substituted item is taken up.<br />

(ii) They must be given in writing.<br />

(iii) They must be signed by the Engineer-in-charge.<br />

33.11.1 Extension of time due to variations in items executed<br />

As regards the extra time for completion of the work due to deviations in agreement items [para 24.1<br />

of this Manual may be referred to], and altered, additional or substituted items, the Engineer-in-charge<br />

should determine the proportion that the algebraic sum of deviated, altered, additional or substituted work<br />

bears to the original contract work and certify for such portion. For substituted items, the additional cost of<br />

modified component only is to be taken. Payment made towards clause 10C/10CA/10CC should not be<br />

considered. He should extend the time for the completion of the work according to such proportion plus<br />

25% thereof. The proportion so determined by the Engineer-in-charge is final, and the contractor cannot<br />

raise a dispute as to such proportion and demand arbitration. However, if the contractor feels that the<br />

period of extension given is, having regard to the proportion so determined miscalculated, it is open to him<br />

to request arbitration under the relevant clause about the propriety or otherwise of such period of extension.<br />

33.11.2 Precautions to be taken during sanction of items<br />

(1) Some times while sanctioning items the Engineer-in-charge gives the impression to the contractor<br />

that although he had recommended higher rates, the Superintending Engineer or the Chief Engineer<br />

has reduced them. It should clearly be borne in mind that under the terms of the contract it is the<br />

Executive Engineer who is the competent authority for according such sanction, and it should be<br />

so worked as to convey clearly to the other party that the items have been sanctioned by him and<br />

not for or at the instance of the higher authority.<br />

(2) Sometimes the Executive Engineer endorses copies of communication addressed by him to the<br />

competent authority for sanctioning rates for certain items, to the contractor concerned. This practice<br />

is irregular and is likely to cause legal complications. All communications in connection with fixation of<br />

rates etc. should be marked “Confidential”, and copies thereof should not be endorsed to the contractor<br />

or any other private party. In reply to the communications of the contractor asking for early settlement<br />

of items, which are required to be examined and sanctioned by higher authorities and the sanction is<br />

awaited, the contractor should not be informed that sanction of the competent authority is awaited.<br />

They should only be informed that the matter is under consideration and is receiving attention.<br />

209

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!