SECTION 33<br />

get measured and accepted by both the parties. Delay in the taking of measurements by the<br />

Engineer-in-charge cannot of course delay the date of completion, since shelter under this provision<br />

cannot be resorted to for the lapse by the party taking advantage of it. Anyhow, if the contractor<br />

delays/avoids finalizing of measurements, application of this provision will be reasonable.<br />

33.8 Clause 10(C) of Forms no. CPWD 7 and 8<br />

(1) Clause 10(C) provides for re-imbursement to contractor due to increase/decrease caused as a<br />

direct result of coming into force of any fresh law or statutory rule or order (but not due to any<br />

changes in sales tax/VAT), in the price of material incorporated in the works (excluding the materials<br />

covered under clause 10CA) and/or wages of labour increased over prices/wages prevailing at<br />

the time of the last stipulated date of receipt of tenders including extensions, of any, for the work<br />

during contract period including the justified period extended under the provisions of clause 5 of<br />

the contract without any action under clause 2. The increase should not be attributable to delay in<br />

the execution of the contract within the control of the contractor. (Modified as per OM/MAN/167)<br />

(2) The operation of the clause includes the increase as well as decrease in price of materials and/or<br />

the wages of labour.<br />

(3) To ensure uniformity in working out the rates so payable, following procedure shall be followed:<br />

(i) Materials:<br />

The Increased/Decreased rates of material(s) shall be approved by Zonal Chief Engineer. Payment/<br />

Recovery shall be made by Engineer-in- Charge on the basis of theoretical consumption of<br />

material(s) multiplied with difference in cost of such material(s) as prevailing at the time of receipt<br />

of tender and increased/decreased rates as approved by Zonal Chief Engineer.<br />

(ii) Labour:<br />

(a) The increase/Decrease shall be approved and Paid/Recovered by Engineer-in-Charge on the<br />

basis of Increase/Decrease of wages of labour coming into force as per fresh law or statutory<br />

rule or order. (Modified as per OM/MAN/167)<br />

(b) The Increase/Decrease labour shall be considered on the minimum daily wages in rupees if<br />

any unskilled adult mazdoor, fixed under any law or statutory rule or order. (Added vide<br />

OM/MAN/167A)<br />

(4) Clause 10(C) forms an exception to the general rule of the contract that nothing more than what<br />

has been agreed to be paid for work done is to be paid to the contractor. It is in the nature of<br />

recompense to the contractor if during the progress of the work the price of any materials<br />

incorporated in the works and/or wages of labour increases as a direct result of the coming into<br />

force of any fresh law or statutory rule. The first thing is that the exception has to be strictly<br />

construed. Secondly, it contains an in-built safeguard because it is in the nature of an equitable<br />

reimbursement.<br />

(5) The claim for increase over and above the prices/wages prevailing at the time of the last<br />

stipulated date of receipt of tenders including extensions, if any, for the work during contract<br />

period including the justified period extended under the provisions of clause 5 of the contract<br />

without any action under clause 2, shall be payable which shall be limited to the prices/wages<br />

prevailing at the time of stipulated date of completion or as prevailing for the period under<br />

consideration, whichever is less. This clause shall not be applicable where clause 10CC is<br />

applicable. (Modified as per OM/MAN/167)<br />

(6) The component of labour for every work have to be predetermined and incorported in schdule<br />

‘F’. This may be done as given in para 33.10.1 of the manual for clause 10CC.<br />

(Added vide OM/MAN/160).<br />